Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2000 |
Principal Product | corrugated packaging |
NAICS | n/a |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 143,000 |
Annual Production | 13,000,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $46,685 | 2,521,395 | kWh | $0.02 |
Electricity Demand | $76,967 | 5,847 | kW-months/year | $13.16 |
Electricity Fees | $205 | - | $ | - |
Natural Gas | $50,280 | 15,000 | MMBtu | $3.35 |
TOTAL ENERGY COSTS | $(-60,919) | |||
RECOMMENDED SAVINGS* | $13,390 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,000 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,600 Cost: $2,200 |
$2,230 | 122,802 | $3,370 | 236 | - | - | - | - | - | - |
$2,230 122,802 kWh |
$3,370 236 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $4,200 Cost: $7,000 |
- | - | $4,200 | 294 | - | - | - | - | - | - |
- - kWh |
$4,200 294 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,400 Cost: $350 |
$700 | 38,687 | $1,060 | 74 | - | - | $(-360) | - | - | - |
$700 38,687 kWh |
$1,060 74 kW-months/year |
- - lb |
$(-360) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,060 Cost: - |
$1,060 | 58,617 | - | - | - | - | - | - | - | - |
$1,060 58,617 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $620 Cost: $100 |
$250 | 13,482 | $370 | 26 | - | - | - | - | - | - |
$250 13,482 kWh |
$370 26 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $470 Cost: - |
$800 | 43,669 | $1,200 | 84 | - | - | $(-140) | - | $(-1,390) | - |
$800 43,669 kWh |
$1,200 84 kW-months/year |
- - lb |
$(-140) - $ |
$(-1,390) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $40 Cost: - |
- | - | - | - | $70 | 97 | - | - | $(-30) | - |
- - kWh |
- - kW-months/year |
$70 97 lb |
- - $ |
$(-30) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,390 Cost: $9,650 |
$5,040 | 277,257 | $10,200 | 714 | $70 | 97 | $(-500) | - | $(-1,420) | - | $5,040 277,257 kWh |
$10,200 714 kW-months/year |
$70 97 lb |
$(-500) - $ |
$(-1,420) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,000 Cost: $2,550 |
$2,930 | 161,489 | $4,430 | 310 | - | - | $(-360) | - | - | - | $2,930 161,489 kWh |
$4,430 310 kW-months/year |
- - lb |
$(-360) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost |