Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2001 |
Principal Product | Sheet Metal |
NAICS | n/a |
SIC | 3444 - Sheet Metalwork |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 121,000 |
Annual Production | 24,000,000 Pounds |
Production Hrs. Annual | 0 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $50,231 | 1,666,700 | kWh | $0.03 |
Electricity Demand | $43,698 | 4,438 | kW-months/year | $9.85 |
Electricity Fees | $864 | - | $ | - |
Natural Gas | $63,472 | 8,155 | MMBtu | $7.78 |
TOTAL ENERGY COSTS | $158,265 | |||
RECOMMENDED SAVINGS* | $34,810 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,040 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,290 Cost: $23,430 |
$6,430 | 176,100 | $4,860 | 493 | - | - | - | - | - | - |
$6,430 176,100 kWh |
$4,860 493 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $6,500 Cost: $21,650 |
$(-160) | (-5,400) | $(-70) | (-7) | $6,730 | 1,212 | - | - | - | - |
$(-160) (-5,400) kWh |
$(-70) (-7) kW-months/year |
$6,730 1,212 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $4,500 Cost: $6,270 |
- | - | - | - | $4,500 | 810 | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,500 810 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $2,960 Cost: $6,500 |
- | - | $2,960 | 300 | - | - | - | - | - | - |
- - kWh |
$2,960 300 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,290 Cost: $360 |
$1,770 | 58,600 | $1,300 | 133 | - | - | $(-780) | - | - | - |
$1,770 58,600 kWh |
$1,300 133 kW-months/year |
- - MMBtu |
$(-780) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.515 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE |
Savings: $7,270 Cost: $8,240 |
- | - | - | - | - | - | - | - | $7,270 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$7,270 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,810 Cost: $66,450 |
$8,040 | 229,300 | $9,050 | 919 | $11,230 | 2,022 | $(-780) | - | $7,270 | - | $8,040 229,300 kWh |
$9,050 919 kW-months/year |
$11,230 2,022 MMBtu |
$(-780) - $ |
$7,270 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,040 Cost: $36,560 |
$8,200 | 234,700 | $9,120 | 926 | $4,500 | 810 | $(-780) | - | - | - | $8,200 234,700 kWh |
$9,120 926 kW-months/year |
$4,500 810 MMBtu |
$(-780) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes |