IAC Assessment: CO0499
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0499
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2002
Principal Product Injection molded plastics parts
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $1,000,000-$5,000,000
# of Employees 56
Plant Area (Sq.Ft.) 44,450
Annual Production 13,900,000 Pieces
Production Hrs. Annual 6,656
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $93,176 2,969,880 kWh $0.03
Electricity Demand $68,242 7,063 kW-months/year $9.66
Electricity Fees $132 - $ -
Natural Gas $3,296 291 MMBtu $11.33
TOTAL ENERGY COSTS $164,846
RECOMMENDED SAVINGS* $136,660 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,820
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$26,240
Cost:
$84,240
$16,870 537,900 $9,370 970 - - - - - - - - $16,870
537,900
kWh
$9,370
970
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$3,480
Cost:
$7,000
- - $3,480 360 - - - - - - - - -
-
kWh
$3,480
360
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$610
Cost:
$260
$620 19,900 $350 36 - - $(-360) - - - - - $620
19,900
kWh
$350
36
kW-months/year
-
-
MMBtu
$(-360)
-
$
-
-
$
-
-
$
04: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE Savings:
$540
Cost:
$900
- - - - $540 48 - - - - - - -
-
kWh
-
-
kW-months/year
$540
48
MMBtu
-
-
$
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$190
Cost:
-
$970 30,900 $590 61 - - $(-460) - - - $(-910) - $970
30,900
kWh
$590
61
kW-months/year
-
-
MMBtu
$(-460)
-
$
-
-
$
$(-910)
-
$
06: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE Savings:
$105,600
Cost:
$120,000
- - - - - - - - $45,600 - $60,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$45,600
-
$
$60,000
-
$
TOTAL RECOMMENDED Savings:
$136,660
Cost:
$212,400
$18,460 588,700 $13,790 1,427 $540 48 $(-820) - $45,600 - $59,090 - $18,460
588,700
kWh
$13,790
1,427
kW-months/year
$540
48
MMBtu
$(-820)
-
$
$45,600
-
$
$59,090
-
$
TOTAL IMPLEMENTED Savings:
$4,820
Cost:
$8,160
$1,590 50,800 $4,420 457 $540 48 $(-820) - - - $(-910) - $1,590
50,800
kWh
$4,420
457
kW-months/year
$540
48
MMBtu
$(-820)
-
$
-
-
$
$(-910)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost