Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2002 |
Principal Product | Finished metal products |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 58,500 |
Annual Production | 120,000 Pieces |
Production Hrs. Annual | 2,730 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $21,974 | 1,327,589 | kWh | $0.02 |
Electricity Demand | $73,284 | 5,447 | kW-months/year | $13.45 |
Electricity Fees | $193 | - | $ | - |
Natural Gas | $80,590 | 12,347 | MMBtu | $6.53 |
TOTAL ENERGY COSTS | $200,954 | |||
RECOMMENDED SAVINGS* | $42,840 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $39,010 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $29,000 Cost: $7,000 |
- | - | $29,000 | 2,160 | - | - | - | - | - | - | - | - |
- - kWh |
$29,000 2,160 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $8,990 Cost: $300 |
- | - | - | - | - | - | - | - | $8,990 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$8,990 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM |
Savings: $2,640 Cost: $5,750 |
$520 | 31,100 | $2,120 | 158 | - | - | - | - | - | - | - | - |
$520 31,100 kWh |
$2,120 158 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,110 Cost: $4,890 |
- | - | - | - | $1,110 | 212 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,110 212 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $730 Cost: $300 |
- | - | - | - | $730 | 139 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$730 139 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $290 Cost: $50 |
$60 | 3,900 | $230 | 17 | - | - | - | - | - | - | - | - |
$60 3,900 kWh |
$230 17 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $80 Cost: - |
$200 | 11,900 | $710 | 53 | - | - | $(-310) | - | - | - | $(-520) | - |
$200 11,900 kWh |
$710 53 kW-months/year |
- - MMBtu |
$(-310) - $ |
- - $ |
$(-520) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $42,840 Cost: $18,290 |
$780 | 46,900 | $32,060 | 2,388 | $1,840 | 351 | $(-310) | - | $8,990 | - | $(-520) | - | $780 46,900 kWh |
$32,060 2,388 kW-months/year |
$1,840 351 MMBtu |
$(-310) - $ |
$8,990 - $ |
$(-520) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $39,010 Cost: $7,650 |
$60 | 3,900 | $29,230 | 2,177 | $730 | 139 | - | - | $8,990 | - | - | - | $60 3,900 kWh |
$29,230 2,177 kW-months/year |
$730 139 MMBtu |
- - $ |
$8,990 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost |