IAC Assessment: CO0508
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0508
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2002
Principal Product Specialty bolts, track spikes for railroads
NAICS n/a
SIC 3452 - Bolts, Nuts, Rivets, And Washers
Sales $5,000,000-$10,000,000
# of Employees 90
Plant Area (Sq.Ft.) 48,750
Annual Production 10,000,000 Pounds
Production Hrs. Annual 4,420
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $118,540 2,416,050 kWh $0.05
Electricity Demand $84,183 9,803 kW-months/year $8.59
Natural Gas $130,798 35,466 MMBtu $3.69
TOTAL ENERGY COSTS $337,681
RECOMMENDED SAVINGS* $159,210 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $40,640
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ gal $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,450
Cost:
$90
$3,260 66,600 $1,550 181 - - $(-360) - - - $3,260
66,600
kWh
$1,550
181
kW-months/year
-
-
gal
$(-360)
-
$
-
-
$
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$4,230
Cost:
$7,000
- - $4,230 492 - - - - - - -
-
kWh
$4,230
492
kW-months/year
-
-
gal
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,570
Cost:
$23,500
$2,460 50,300 $1,110 129 - - - - - - $2,460
50,300
kWh
$1,110
129
kW-months/year
-
-
gal
-
-
$
-
-
$
04: 3.3122 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS Savings:
$31,960
Cost:
$1,620
- - - - $3,330 6,400 - - $28,630 - -
-
kWh
-
-
kW-months/year
$3,330
6,400
gal
-
-
$
$28,630
-
$
05: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL Savings:
$115,000
Cost:
$100,000
- - - - - - $120,000 - $(-5,000) - -
-
kWh
-
-
kW-months/year
-
-
gal
$120,000
-
$
$(-5,000)
-
$
TOTAL RECOMMENDED Savings:
$159,210
Cost:
$132,210
$5,720 116,900 $6,890 802 $3,330 6,400 $119,640 - $23,630 - $5,720
116,900
kWh
$6,890
802
kW-months/year
$3,330
6,400
gal
$119,640
-
$
$23,630
-
$
TOTAL IMPLEMENTED Savings:
$40,640
Cost:
$8,710
$3,260 66,600 $5,780 673 $3,330 6,400 $(-360) - $28,630 - $3,260
66,600
kWh
$5,780
673
kW-months/year
$3,330
6,400
gal
$(-360)
-
$
$28,630
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ $ $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Ancillary Material Cost