Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2002 |
Principal Product | Semiconductor materials |
NAICS | n/a |
SIC | 3674 - Semiconductors And Related Devices |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 27,000 |
Annual Production | 250,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $199,247 | 5,208,600 | kWh | $0.04 |
Electricity Demand | $87,448 | 19,085 | kW-months/year | $4.58 |
Electricity Fees | $8,808 | - | $ | - |
Natural Gas | $25,096 | 4,204 | MMBtu | $5.97 |
TOTAL ENERGY COSTS | $328,679 | |||
RECOMMENDED SAVINGS* | $36,120 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,420 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM |
Savings: $12,040 Cost: $9,500 |
$8,560 | 294,200 | $3,480 | 479 | - | - | - | - |
$8,560 294,200 kWh |
$3,480 479 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $10,160 Cost: $14,010 |
- | - | $10,160 | 1,394 | - | - | - | - |
- - kWh |
$10,160 1,394 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,380 Cost: $990 |
$4,380 | 150,600 | - | - | - | - | - | - |
$4,380 150,600 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $4,020 Cost: - |
$2,990 | 102,700 | $1,030 | 141 | - | - | - | - |
$2,990 102,700 kWh |
$1,030 141 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,420 Cost: $190 |
$2,070 | 71,200 | $710 | 98 | $(-360) | - | - | - |
$2,070 71,200 kWh |
$710 98 kW-months/year |
$(-360) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $2,290 Cost: $1,200 |
- | - | $3,490 | 480 | - | - | $(-1,200) | - |
- - kWh |
$3,490 480 kW-months/year |
- - $ |
$(-1,200) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $370 Cost: $300 |
$280 | 9,500 | $90 | 13 | - | - | - | - |
$280 9,500 kWh |
$90 13 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $340 Cost: - |
$1,070 | 36,000 | $480 | 67 | $20 | - | $(-1,230) | - |
$1,070 36,000 kWh |
$480 67 kW-months/year |
$20 - $ |
$(-1,230) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $100 Cost: - |
$100 | 3,600 | - | - | - | - | - | - |
$100 3,600 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $36,120 Cost: $26,190 |
$19,450 | 667,800 | $19,440 | 2,672 | $(-340) | - | $(-2,430) | - | $19,450 667,800 kWh |
$19,440 2,672 kW-months/year |
$(-340) - $ |
$(-2,430) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,420 Cost: $190 |
$2,070 | 71,200 | $710 | 98 | $(-360) | - | - | - | $2,070 71,200 kWh |
$710 98 kW-months/year |
$(-360) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes |