Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2006 |
Principal Product | Concrete pipe |
NAICS | 327332 - Concrete Pipe Manufacturing |
SIC | 3272 - Concrete Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 104,000 |
Annual Production | 230,000 Tons |
Production Hrs. Annual | 3,146 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $89,228 | 2,602,575 | kWh | $0.03 |
Electricity Demand | $118,268 | 8,930 | kW-months/year | $13.24 |
Electricity Fees | $2,096 | - | $ | - |
Natural Gas | $162,918 | 18,021 | MMBtu | $9.04 |
TOTAL ENERGY COSTS | $372,510 | |||
RECOMMENDED SAVINGS* | $25,404 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,124 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $4,250 Cost: $4,140 |
- | - | - | - | $4,250 | 507 | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,250 507 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,000 Cost: $270 |
$1,120 | 36,800 | $2,880 | 228 | - | - | - | - | - | - |
$1,120 36,800 kWh |
$2,880 228 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $3,370 Cost: $650 |
- | - | - | - | $3,370 | 402 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,370 402 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $400 Cost: $400 |
$150 | 4,800 | $250 | 20 | - | - | - | - | - | - |
$150 4,800 kWh |
$250 20 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $54 Cost: $171 |
$21 | 688 | $33 | 3 | - | - | - | - | - | - |
$21 688 kWh |
$33 3 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $5,370 Cost: $4,040 |
- | - | - | - | $5,370 | 640 | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,370 640 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,050 Cost: $14,465 |
$2,330 | 76,700 | $2,480 | 196 | - | - | $140 | - | $100 | - |
$2,330 76,700 kWh |
$2,480 196 kW-months/year |
- - MMBtu |
$140 - $ |
$100 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,700 Cost: $3,100 |
$640 | 20,900 | $1,010 | 80 | - | - | $30 | - | $20 | - |
$640 20,900 kWh |
$1,010 80 kW-months/year |
- - MMBtu |
$30 - $ |
$20 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $1,210 Cost: $2,950 |
$430 | 14,100 | $780 | 62 | - | - | - | - | - | - |
$430 14,100 kWh |
$780 62 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,404 Cost: $30,186 |
$4,691 | 153,988 | $7,433 | 589 | $12,990 | 1,549 | $170 | - | $120 | - | $4,691 153,988 kWh |
$7,433 589 kW-months/year |
$12,990 1,549 MMBtu |
$170 - $ |
$120 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,124 Cost: $20,096 |
$3,621 | 118,988 | $5,643 | 447 | $7,620 | 909 | $140 | - | $100 | - | $3,621 118,988 kWh |
$5,643 447 kW-months/year |
$7,620 909 MMBtu |
$140 - $ |
$100 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |