Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2006 |
Principal Product | Concrete pipe |
NAICS | 327332 - Concrete Pipe Manufacturing |
SIC | 3272 - Concrete Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 11 |
Plant Area (Sq.Ft.) | 16,000 |
Annual Production | 40,000 Tons |
Production Hrs. Annual | 2,622 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $15,356 | 393,200 | kWh | $0.04 |
Electricity Demand | $20,777 | 2,994 | kW-months/year | $6.94 |
Electricity Fees | $813 | - | $ | - |
Natural Gas | $39,470 | 4,130 | MMBtu | $9.56 |
TOTAL ENERGY COSTS | $76,416 | |||
RECOMMENDED SAVINGS* | $19,710 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $4,730 Cost: $3,350 |
- | - | - | - | $4,730 | 512 | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,730 512 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $4,550 Cost: $11,320 |
- | - | $4,550 | 437 | - | - | - | - | - | - |
- - kWh |
$4,550 437 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,300 Cost: $6,900 |
$1,520 | 37,200 | $1,780 | 170 | - | - | - | - | - | - |
$1,520 37,200 kWh |
$1,780 170 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $150 Cost: $442 |
$60 | 1,365 | $90 | 9 | - | - | - | - | - | - |
$60 1,365 kWh |
$90 9 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $380 Cost: - |
- | - | - | - | $380 | 41 | - | - | - | - |
- - kWh |
- - kW-months/year |
$380 41 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $3,200 Cost: $5,050 |
- | - | - | - | $3,200 | 347 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,200 347 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $1,100 Cost: $2,950 |
$620 | 15,200 | $480 | 46 | - | - | - | - | - | - |
$620 15,200 kWh |
$480 46 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $990 Cost: $3,420 |
$450 | 10,900 | $520 | 50 | - | - | - | - | $20 | - |
$450 10,900 kWh |
$520 50 kW-months/year |
- - MMBtu |
- - $ |
$20 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $950 Cost: $500 |
- | - | - | - | - | - | $950 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$950 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $360 Cost: $90 |
- | - | - | - | $360 | 39 | - | - | - | - |
- - kWh |
- - kW-months/year |
$360 39 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $19,710 Cost: $34,022 |
$2,650 | 64,665 | $7,420 | 712 | $8,670 | 939 | $950 | - | $20 | - | $2,650 64,665 kWh |
$7,420 712 kW-months/year |
$8,670 939 MMBtu |
$950 - $ |
$20 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost |