IAC Assessment: CO0619
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0619
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2009
Principal Product Aircraft Engine & Turbine Generator Controls
NAICS 336412 - Aircraft Engine and Engine Parts Manufacturing
SIC 3724 - Aircraft Engines And Engine Parts
Sales $100,000,000-$500,000,000
# of Employees 600
Plant Area (Sq.Ft.) 200,000
Annual Production 300,000 Pieces
Production Hrs. Annual 6,120
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $398,234 12,527,136 kWh $0.03
Electricity Demand $324,179 35,610 kW-months/year $9.10
Electricity Fees $3,360 - $ -
Natural Gas $121,648 14,674 MMBtu $8.29
TOTAL ENERGY COSTS $847,421
RECOMMENDED SAVINGS* $40,430 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $39,640
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$37,130
Cost:
$140,000
$37,130 1,114,000 - - - - - - $37,130
1,114,000
kWh
-
-
kW-months/year
-
-
$
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$270
Cost:
$580
$190 5,634 $80 8 - - - - $190
5,634
kWh
$80
8
kW-months/year
-
-
$
-
-
$
03: 2.7134 USE PHOTOCELL CONTROLS Savings:
$1,710
Cost:
$20,000
$970 29,000 $380 38 $110 - $250 - $970
29,000
kWh
$380
38
kW-months/year
$110
-
$
$250
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$790
Cost:
$2,150
$90 2,600 $40 4 $370 - $290 - $90
2,600
kWh
$40
4
kW-months/year
$370
-
$
$290
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$530
Cost:
$400
$240 7,300 $100 10 $160 - $30 - $240
7,300
kWh
$100
10
kW-months/year
$160
-
$
$30
-
$
TOTAL RECOMMENDED Savings:
$40,430
Cost:
$163,130
$38,620 1,158,534 $600 60 $640 - $570 - $38,620
1,158,534
kWh
$600
60
kW-months/year
$640
-
$
$570
-
$
TOTAL IMPLEMENTED Savings:
$39,640
Cost:
$160,980
$38,530 1,155,934 $560 56 $270 - $280 - $38,530
1,155,934
kWh
$560
56
kW-months/year
$270
-
$
$280
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost