IAC Assessment: CO0650
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0650
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2011
Principal Product Thermoformed plastic parts
NAICS 326199 - All Other Plastics Product Manufacturing
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 65
Plant Area (Sq.Ft.) 76,000
Annual Production 150,000,000 Pounds
Production Hrs. Annual 4,160
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $75,324 1,970,453 kWh $0.04
Electricity Demand $193,320 10,171 kW-months/year $19.01
Electricity Fees $1,806 - $ -
Natural Gas $16,518 2,253 MMBtu $7.33
TOTAL ENERGY COSTS $286,968
RECOMMENDED SAVINGS* $14,230 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,250
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$4,700
Cost:
$1,000
- - $4,700 246 - - - - - - - - -
-
kWh
$4,700
246
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,390
Cost:
$190
$610 14,300 $780 41 - - - - - - - - $610
14,300
kWh
$780
41
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,420
Cost:
$9,240
$2,270 42,900 $1,970 103 - - $140 - - - $40 - $2,270
42,900
kWh
$1,970
103
kW-months/year
-
-
MMBtu
$140
-
$
-
-
$
$40
-
$
04: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$2,980
Cost:
$24,500
$1,580 15,600 - - - - - - $1,400 - - - $1,580
15,600
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$1,400
-
$
-
-
$
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$740
Cost:
$1,470
$(-40) (-900) $(-20) (-1) $800 119 - - - - - - $(-40)
(-900)
kWh
$(-20)
(-1)
kW-months/year
$800
119
MMBtu
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$14,230
Cost:
$36,400
$4,420 71,900 $7,430 389 $800 119 $140 - $1,400 - $40 - $4,420
71,900
kWh
$7,430
389
kW-months/year
$800
119
MMBtu
$140
-
$
$1,400
-
$
$40
-
$
TOTAL IMPLEMENTED Savings:
$11,250
Cost:
$11,900
$2,840 56,300 $7,430 389 $800 119 $140 - - - $40 - $2,840
56,300
kWh
$7,430
389
kW-months/year
$800
119
MMBtu
$140
-
$
-
-
$
$40
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost