Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2015 |
Principal Product | Bakery Products |
NAICS | 311812 - Commercial Bakeries |
SIC | 2051 - Bread, Cake, And Related Products |
Sales | $5,000,000-$10,000,000 |
# of Employees | 140 |
Plant Area (Sq.Ft.) | 52,000 |
Annual Production | 33,770,240 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $153,484 | 3,446,893 | kWh | $0.04 |
Electricity Demand | $136,169 | 6,454 | kW-months/year | $21.10 |
Electricity Fees | $607 | - | $ | - |
Natural Gas | $180,871 | 32,434 | MMBtu | $5.58 |
TOTAL ENERGY COSTS | $471,131 | |||
RECOMMENDED SAVINGS* | $23,370 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,740 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,270 Cost: $310 |
$4,350 | 97,800 | $3,920 | 188 | - | - | - | - |
$4,350 97,800 kWh |
$3,920 188 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $4,050 Cost: $4,240 |
$2,130 | 47,800 | $1,920 | 92 | - | - | - | - |
$2,130 47,800 kWh |
$1,920 92 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,830 Cost: $60 |
$1,490 | 33,500 | $1,340 | 65 | - | - | - | - |
$1,490 33,500 kWh |
$1,340 65 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2626 AVOID FROST FORMATION ON EVAPORATORS |
Savings: $1,750 Cost: $1,890 |
$1,750 | 39,300 | - | - | - | - | - | - |
$1,750 39,300 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $900 Cost: $4,090 |
$540 | 12,100 | $360 | 17 | - | - | - | - |
$540 12,100 kWh |
$360 17 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,570 Cost: $9,010 |
$2,890 | 65,000 | $2,610 | 125 | $60 | - | $10 | - |
$2,890 65,000 kWh |
$2,610 125 kW-months/year |
$60 - $ |
$10 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,370 Cost: $19,600 |
$13,150 | 295,500 | $10,150 | 487 | $60 | - | $10 | - | $13,150 295,500 kWh |
$10,150 487 kW-months/year |
$60 - $ |
$10 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,740 Cost: $13,410 |
$7,780 | 174,900 | $6,890 | 330 | $60 | - | $10 | - | $7,780 174,900 kWh |
$6,890 330 kW-months/year |
$60 - $ |
$10 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost |