Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2016 |
Principal Product | Tungsten Carbide Powder |
NAICS | 331492 - Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum) |
SIC | 3341 - Secondary Nonferrous Metals |
Sales | $1,000,000-$5,000,000 |
# of Employees | 15 |
Plant Area (Sq.Ft.) | 51,200 |
Annual Production | 500 Tons |
Production Hrs. Annual | 4,160 |
Location (State) | MT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $149,342 | 1,875,960 | kWh | $0.08 |
Electricity Demand | $88,396 | 9,466 | kW-months/year | $9.34 |
Electricity Fees | $324 | - | $ | - |
Natural Gas | $17,436 | 3,031 | MMBtu | $5.75 |
TOTAL ENERGY COSTS | $299,188 | |||
RECOMMENDED SAVINGS* | $34,690 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $8,690 Cost: $100 |
$3,080 | 38,700 | $5,610 | 601 | - | - | - | - | - | - | - | - |
$3,080 38,700 kWh |
$5,610 601 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,970 Cost: $1,390 |
$5,210 | 65,500 | $1,760 | 189 | - | - | - | - | - | - | - | - |
$5,210 65,500 kWh |
$1,760 189 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $6,010 Cost: $620 |
$2,140 | 26,900 | $3,870 | 414 | - | - | - | - | - | - | - | - |
$2,140 26,900 kWh |
$3,870 414 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6112 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME |
Savings: $5,930 Cost: $24,000 |
$(-510) | (-6,400) | $(-750) | (-80) | $(-1,110) | (-194) | $8,300 | 91,200 | - | - | - | - |
$(-510) (-6,400) kWh |
$(-750) (-80) kW-months/year |
$(-1,110) (-194) MMBtu |
$8,300 91,200 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,040 Cost: $13,050 |
$2,950 | 37,100 | $1,030 | 110 | - | - | - | - | $30 | - | $30 | - |
$2,950 37,100 kWh |
$1,030 110 kW-months/year |
- - MMBtu |
- - lb |
$30 - $ |
$30 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $3,050 Cost: $2,950 |
$2,380 | 30,000 | $670 | 72 | - | - | - | - | - | - | - | - |
$2,380 30,000 kWh |
$670 72 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,690 Cost: $42,110 |
$15,250 | 191,800 | $12,190 | 1,306 | $(-1,110) | (-194) | $8,300 | 91,200 | $30 | - | $30 | - | $15,250 191,800 kWh |
$12,190 1,306 kW-months/year |
$(-1,110) (-194) MMBtu |
$8,300 91,200 lb |
$30 - $ |
$30 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Ancillary Material Cost |