Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2010 |
Principal Product | Chromatogrphs and spectrometers |
NAICS | 339112 - Surgical and Medical Instrument Manufacturing |
SIC | 3841 - Surgical And Medical Instruments |
Sales | $100,000,000-$500,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 131,770 |
Annual Production | 1 Units |
Production Hrs. Annual | 3,120 |
Location (State) | DE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,564,256 | 13,812,707 | kWh | $0.11 |
Natural Gas | $119,599 | 8,215 | MMBtu | $14.56 |
TOTAL ENERGY COSTS | $1,683,855 | |||
RECOMMENDED SAVINGS* | $441,945 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $156,800 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7314 REDUCE VENTILATION AIR |
Savings: $152,300 Cost: $500,000 |
$126,560 | 1,120,000 | $25,740 | 1,822 |
$126,560 1,120,000 kWh |
$25,740 1,822 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7235 INSTALL FOSSIL FUEL MAKE-UP AIR UNIT |
Savings: $95,200 Cost: $250,000 |
$217,600 | 1,925,000 | $(-122,400) | (-8,690) |
$217,600 1,925,000 kWh |
$(-122,400) (-8,690) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $143,000 Cost: $4,268 |
$143,000 | 567,750 | - | - |
$143,000 567,750 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7122 DISCONNECT BALLASTS |
Savings: $12,500 Cost: $350 |
$12,500 | 111,000 | - | - |
$12,500 111,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $11,800 Cost: $250 |
$11,800 | 105,000 | - | - |
$11,800 105,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $10,400 Cost: $100 |
$10,400 | 92,000 | - | - |
$10,400 92,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,080 Cost: $6,300 |
$6,080 | 53,800 | - | - |
$6,080 53,800 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,000 Cost: $7,644 |
$2,000 | 43,350 | - | - |
$2,000 43,350 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4222 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN |
Savings: $4,200 Cost: $10,000 |
$4,200 | 32,270 | - | - |
$4,200 32,270 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,110 Cost: $18,280 |
$2,110 | 18,600 | - | - |
$2,110 18,600 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,215 Cost: $2,500 |
$1,215 | 10,750 | - | - |
$1,215 10,750 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,140 Cost: $5,050 |
$1,140 | 10,100 | - | - |
$1,140 10,100 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $441,945 Cost: $804,742 |
$538,605 | 4,089,620 | $(-96,660) | (-6,868) | $538,605 4,089,620 kWh |
$(-96,660) (-6,868) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $156,800 Cost: $12,162 |
$156,800 | 716,100 | - | - | $156,800 716,100 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |