Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2023 |
Principal Product | Optical fiber and optoelectronic devices |
NAICS | 334413 - Semiconductor and Related Device Manufacturing |
SIC | 3674 - Semiconductors And Related Devices |
Sales | $100,000,000-$500,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 166,000 |
Annual Production | 2,257,288 Units |
Production Hrs. Annual | 4,450 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $879,344 | 6,380,263 | kWh | $0.14 |
Electricity Demand | $98,516 | 13,019 | kW-months/year | $7.57 |
Electricity Fees | $176 | - | $ | - |
Natural Gas | $65,526 | 5,592 | MMBtu | $11.72 |
TOTAL ENERGY COSTS | $1,043,562 | |||
RECOMMENDED SAVINGS* | $164,668 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $96,454 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $84,324 Cost: - |
$84,324 | 551,140 | - | - |
$84,324 551,140 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2211 USE OPTIMUM TEMPERATURE |
Savings: $6,980 Cost: - |
$6,980 | 45,620 | - | - |
$6,980 45,620 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $4,020 Cost: - |
- | - | $4,020 | 343 |
- - kWh |
$4,020 343 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $10,928 Cost: - |
$5,349 | 34,962 | $5,579 | 476 |
$5,349 34,962 kWh |
$5,579 476 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $16,704 Cost: - |
$16,704 | 109,178 | - | - |
$16,704 109,178 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $14,418 Cost: - |
$14,418 | 94,233 | - | - |
$14,418 94,233 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $3,578 Cost: - |
$3,578 | 23,383 | - | - |
$3,578 23,383 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $4,694 Cost: - |
$4,694 | 30,681 | - | - |
$4,694 30,681 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $6,332 Cost: $20,000 |
$6,332 | 41,384 | - | - |
$6,332 41,384 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $6,153 Cost: $9,740 |
- | - | $6,153 | 525 |
- - kWh |
$6,153 525 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,387 Cost: $6,500 |
- | - | $1,387 | 118 |
- - kWh |
$1,387 118 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,150 Cost: $8,994 |
$5,150 | 33,660 | - | - |
$5,150 33,660 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $164,668 Cost: $45,234 |
$147,529 | 964,241 | $17,139 | 1,462 | $147,529 964,241 kWh |
$17,139 1,462 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $96,454 Cost: $8,994 |
$96,454 | 630,420 | - | - | $96,454 630,420 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |