Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | South Dakota State |
---|---|
Assessment Year | 1995 |
Principal Product | Headsets, Earsets, Intercoms, Circuit Boards |
NAICS | n/a |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 57,500 |
Annual Production | 1,840,000 Pieces |
Production Hrs. Annual | 2,600 |
Location (State) | MN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $40,501 | 594,080 | kWh | $0.07 |
Natural Gas | $4,745 | 962 | MMBtu | $4.93 |
TOTAL ENERGY COSTS | $45,246 | |||
RECOMMENDED SAVINGS* | $12,780 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,525 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Electricity Usage | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,278 Cost: $16,954 |
$5,278 | 90,563 | - | - | - | - |
$5,278 90,563 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $132 Cost: $380 |
$132 | 4,982 | - | - | - | - |
$132 4,982 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $783 Cost: $1,350 |
- | - | $783 | 160 | - | - |
- - kWh |
$783 160 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $53 Cost: $120 |
$53 | 2,052 | - | - | - | - |
$53 2,052 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $689 Cost: $2,805 |
$689 | 4,396 | - | - | - | - |
$689 4,396 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4112 RECOVERY METALS FROM RINSE WATER(EVAP., ION EXCHANGE, RO, ELECTROLYSIS, ELECTRODIALYSIS) AND REUSE RINSE WATER |
Savings: $5,845 Cost: $7,342 |
- | - | - | - | $5,845 | - |
- - kWh |
- - MMBtu |
$5,845 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,780 Cost: $28,951 |
$6,152 | 101,993 | $783 | 160 | $5,845 | - | $6,152 101,993 kWh |
$783 160 MMBtu |
$5,845 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,525 Cost: $4,275 |
$742 | 6,448 | $783 | 160 | - | - | $742 6,448 kWh |
$783 160 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Electricity Usage | Natural Gas | Water Disposal |