IAC Assessment: DS0116
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DS0116
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center South Dakota State
Assessment Year 1998
Principal Product Commercial and Packaging Printing
NAICS n/a
SIC 2752 - Commercial Printing, Lithographic
Sales $10,000,000-$50,000,000
# of Employees 202
Plant Area (Sq.Ft.) 67,000
Annual Production 72,622 Pounds
Production Hrs. Annual 7,488
Location (State) MN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $126,724 3,851,407 kWh $0.03
Electricity Demand $65,651 8,676 kW-months/year $7.57
Electricity Fees $15,962 - $ -
Natural Gas $4,394 696 MMBtu $6.31
TOTAL ENERGY COSTS $251,207
RECOMMENDED SAVINGS* $32,041 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ $ $ lb $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,230
Cost:
$9,336
$2,778 84,115 $1,452 192 - - - - - - - - $2,778
84,115
kWh
$1,452
192
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$7,178
Cost:
$3,250
- - - - $7,178 - - - - - - - -
-
kWh
-
-
kW-months/year
$7,178
-
$
-
-
lb
-
-
$
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$664
Cost:
$600
$483 14,654 $181 24 - - - - - - - - $483
14,654
kWh
$181
24
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,290
Cost:
$662
$1,290 38,980 - - - - - - - - - - $1,290
38,980
kWh
-
-
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$464
Cost:
$24
$464 14,068 - - - - - - - - - - $464
14,068
kWh
-
-
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
06: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$6,945
Cost:
$3,518
- - - - - - $1,703 10,880 $(-3,052) - $8,294 - -
-
kWh
-
-
kW-months/year
-
-
$
$1,703
10,880
lb
$(-3,052)
-
$
$8,294
-
$
07: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$3,470
Cost:
$4,750
- - - - - - $3,470 104,000 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$3,470
104,000
lb
-
-
$
-
-
$
08: 3.2176 INCREASE USE OF AUTOMATION Savings:
$7,800
Cost:
$4,900
- - - - - - - - $7,800 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
lb
$7,800
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$32,041
Cost:
$27,040
$5,015 151,817 $1,633 216 $7,178 - $5,173 114,880 $4,748 - $8,294 - $5,015
151,817
kWh
$1,633
216
kW-months/year
$7,178
-
$
$5,173
114,880
lb
$4,748
-
$
$8,294
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ lb $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Personnel Changes Primary Raw Material