IAC Assessment: DS0118
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DS0118
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center South Dakota State
Assessment Year 1998
Principal Product Rollformed Steel Roofing
NAICS n/a
SIC 3316 - Cold Finishing Of Steel Shapes
Sales $10,000,000-$50,000,000
# of Employees 50
Plant Area (Sq.Ft.) 98,550
Annual Production 45,000,000 Pounds
Production Hrs. Annual 4,992
Location (State) MN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $25,242 734,174 kWh $0.03
Electricity Demand $14,765 2,040 kW-months/year $7.24
Electricity Fees $744 - $ -
Natural Gas $15,620 3,045 MMBtu $5.13
LPG $4,781 629 MMBtu $7.60
TOTAL ENERGY COSTS $43,702
RECOMMENDED SAVINGS* $10,260 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,188
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,578
Cost:
$5,326
$1,584 46,600 $994 132 - - - - - - $1,584
46,600
kWh
$994
132
kW-months/year
-
-
$
-
-
$
-
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$610
Cost:
$600
- - - - $610 - - - - - -
-
kWh
-
-
kW-months/year
$610
-
$
-
-
$
-
-
$
03: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$3,300
Cost:
$160
- - - - - - - - $3,300 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$3,300
-
$
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$1,400
Cost:
$2,200
- - - - - - - - $1,400 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$1,400
-
$
05: 3.1172 REVISE RAW MATERIAL SPECS Savings:
$2,372
Cost:
-
- - - - - - $2,372 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$2,372
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$10,260
Cost:
$8,286
$1,584 46,600 $994 132 $610 - $2,372 - $4,700 - $1,584
46,600
kWh
$994
132
kW-months/year
$610
-
$
$2,372
-
$
$4,700
-
$
TOTAL IMPLEMENTED Savings:
$3,188
Cost:
$5,926
$1,584 46,600 $994 132 $610 - - - - - $1,584
46,600
kWh
$994
132
kW-months/year
$610
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes