Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1983 |
Principal Product | DAIRY PRODUCTS |
NAICS | n/a |
SIC | 2026 - Fluid Milk |
Sales | $10,000,000-$50,000,000 |
# of Employees | 242 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 15,000 Thousand Gallons |
Production Hrs. Annual | 4,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $292,095 | 6,544,256 | kWh | $0.04 |
Natural Gas | $124,586 | 31,439 | MMBtu | $3.96 |
TOTAL ENERGY COSTS | $416,681 | |||
RECOMMENDED SAVINGS* | $40,280 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2694 USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE |
Savings: $10,509 Cost: - |
$10,509 | 448,417 | - | - |
$10,509 448,417 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $7,694 Cost: $100 |
- | - | $7,694 | 2,000 |
- - kWh |
$7,694 2,000 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $12,395 Cost: $27,500 |
- | - | $12,395 | 2,718 |
- - kWh |
$12,395 2,718 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,407 Cost: $17,255 |
$3,407 | 76,495 | - | - |
$3,407 76,495 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,275 Cost: $29,686 |
$6,275 | 140,973 | - | - |
$6,275 140,973 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,280 Cost: $74,541 |
$20,191 | 665,885 | $20,089 | 4,718 | $20,191 665,885 kWh |
$20,089 4,718 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |