IAC Assessment: GT0507
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0507
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 1993
Principal Product Men's Slacks
NAICS n/a
SIC 2325 - Men's and Boys' Separate Trousers and Slacks
Sales $1,000,000-$5,000,000
# of Employees 175
Plant Area (Sq.Ft.) 40,000
Annual Production 240,000 Pieces
Production Hrs. Annual 2,040
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $78,068 748,242 kWh $0.10
Natural Gas $21,395 4,112 MMBtu $5.20
TOTAL ENERGY COSTS $99,463
RECOMMENDED SAVINGS* $13,030 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,190
Cost:
$7,340
$3,190 31,360 - - $3,190
31,360
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,710
Cost:
$22,550
$4,710 45,721 - - $4,710
45,721
kWh
-
-
MMBtu
03: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$1,840
Cost:
-
- - $1,840 - -
-
kWh
$1,840
-
MMBtu
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$280
Cost:
-
$280 2,638 - - $280
2,638
kWh
-
-
MMBtu
05: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$3,010
Cost:
$6,250
$3,010 28,722 - - $3,010
28,722
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$13,030
Cost:
$36,140
$11,190 108,441 $1,840 - $11,190
108,441
kWh
$1,840
-
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas