Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1996 |
Principal Product | Packaging Supplies |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 168 |
Plant Area (Sq.Ft.) | 170,000 |
Annual Production | 18,641,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $106,751 | 4,357,269 | kWh | $0.02 |
Electricity Demand | $160,706 | 10,223 | kW-months/year | $15.72 |
Electricity Fees | $13,373 | - | $ | - |
Natural Gas | $57,438 | 9,687 | MMBtu | $5.93 |
TOTAL ENERGY COSTS | $343,168 | |||
RECOMMENDED SAVINGS* | $65,706 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $39,485 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,450 Cost: $19,650 |
$1,924 | 78,546 | $2,322 | 148 | $204 | - | - | - | - | - |
$1,924 78,546 kWh |
$2,322 148 kW-months/year |
$204 - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $670 Cost: $640 |
$294 | 12,016 | $360 | 23 | $16 | - | - | - | - | - |
$294 12,016 kWh |
$360 23 kW-months/year |
$16 - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $21,300 Cost: $2,500 |
$9,119 | 372,216 | $11,160 | 710 | $1,021 | - | - | - | - | - |
$9,119 372,216 kWh |
$11,160 710 kW-months/year |
$1,021 - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $1,390 Cost: $900 |
- | - | - | - | - | - | $1,390 | 234 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,390 234 MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $5,100 Cost: $5,200 |
$5,100 | 208,089 | - | - | - | - | - | - | - | - |
$5,100 208,089 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $20,711 Cost: $16,120 |
$22,934 | 936,108 | $28,079 | 1,786 | - | - | $(-30,302) | (-5,110) | - | - |
$22,934 936,108 kWh |
$28,079 1,786 kW-months/year |
- - $ |
$(-30,302) (-5,110) MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $1,060 Cost: - |
- | - | $1,008 | 36 | $52 | - | - | - | - | - |
- - kWh |
$1,008 36 kW-months/year |
$52 - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5217 REUSE / RECYCLE/ SELL PAPER PRODUCTS |
Savings: $11,025 Cost: $4,850 |
- | - | - | - | - | - | - | - | $11,025 | 350,000 |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$11,025 350,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $65,706 Cost: $49,860 |
$39,371 | 1,606,975 | $42,929 | 2,703 | $1,293 | - | $(-28,912) | (-4,876) | $11,025 | 350,000 | $39,371 1,606,975 kWh |
$42,929 2,703 kW-months/year |
$1,293 - $ |
$(-28,912) (-4,876) MMBtu |
$11,025 350,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $39,485 Cost: $14,090 |
$14,513 | 592,321 | $11,520 | 733 | $1,037 | - | $1,390 | 234 | $11,025 | 350,000 | $14,513 592,321 kWh |
$11,520 733 kW-months/year |
$1,037 - $ |
$1,390 234 MMBtu |
$11,025 350,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) |