IAC Assessment: GT0603
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0603
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 1996
Principal Product Carbon and SS Flat Bar
NAICS n/a
SIC 3316 - Cold Finishing Of Steel Shapes
Sales $10,000,000-$50,000,000
# of Employees 25
Plant Area (Sq.Ft.) 25,500
Annual Production 9,000,000 Pounds
Production Hrs. Annual 2,500
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $37,189 529,894 kWh $0.07
Electricity Demand $18,917 825 kW-months/year $22.93
Electricity Fees $5,201 - $ -
TOTAL ENERGY COSTS $61,507
RECOMMENDED SAVINGS* $13,941 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,941
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Other Liquid (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Other Liquid (non-haz) Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ gal $ $
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$8,880
Cost:
-
- - - - - - - - $8,880 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
gal
$8,880
-
$
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$1,300
Cost:
$1,200
- - $1,300 87 - - - - - - -
-
kWh
$1,300
87
kW-months/year
-
-
$
-
-
gal
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,071
Cost:
$3,036
$424 12,896 $531 59 $116 - - - - - $424
12,896
kWh
$531
59
kW-months/year
$116
-
$
-
-
gal
-
-
$
04: 2.7134 USE PHOTOCELL CONTROLS Savings:
$490
Cost:
$160
$140 4,396 $350 42 - - - - - - $140
4,396
kWh
$350
42
kW-months/year
-
-
$
-
-
gal
-
-
$
05: 2.5111 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS Savings:
$2,200
Cost:
$3,500
- - - - - - $200 200 $2,000 - -
-
kWh
-
-
kW-months/year
-
-
$
$200
200
gal
$2,000
-
$
TOTAL RECOMMENDED Savings:
$13,941
Cost:
$7,896
$564 17,292 $2,181 188 $116 - $200 200 $10,880 - $564
17,292
kWh
$2,181
188
kW-months/year
$116
-
$
$200
200
gal
$10,880
-
$
TOTAL IMPLEMENTED Savings:
$13,941
Cost:
$7,896
$564 17,292 $2,181 188 $116 - $200 200 $10,880 - $564
17,292
kWh
$2,181
188
kW-months/year
$116
-
$
$200
200
gal
$10,880
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ gal $ $
Electricity Usage Electricity Demand Electricity Fees Other Liquid (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Other Liquid (non-haz) Ancillary Material Cost