IAC Assessment: GT0604
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0604
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 1996
Principal Product Billboards
NAICS n/a
SIC 3317 - Steel Pipe And Tubes
Sales $10,000,000-$50,000,000
# of Employees 18
Plant Area (Sq.Ft.) 50,000
Annual Production 1,000 Pieces
Production Hrs. Annual 6,000
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $31,558 390,094 kWh $0.08
Electricity Demand $17,099 1,231 kW-months/year $13.89
Electricity Fees $4,027 - $ -
Natural Gas $3,887 669 MMBtu $5.81
TOTAL ENERGY COSTS $56,571
RECOMMENDED SAVINGS* $25,864 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,444
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost
$ kWh $ kW-months/year $ $
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$4,940
Cost:
-
- - - - $4,940 - -
-
kWh
-
-
kW-months/year
$4,940
-
$
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$720
Cost:
$300
- - $720 48 - - -
-
kWh
$720
48
kW-months/year
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,504
Cost:
$11,400
$3,784 103,751 $1,720 208 - - $3,784
103,751
kWh
$1,720
208
kW-months/year
-
-
$
04: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$14,700
Cost:
$5,000
- - - - $14,700 - -
-
kWh
-
-
kW-months/year
$14,700
-
$
TOTAL RECOMMENDED Savings:
$25,864
Cost:
$16,700
$3,784 103,751 $2,440 256 $19,640 - $3,784
103,751
kWh
$2,440
256
kW-months/year
$19,640
-
$
TOTAL IMPLEMENTED Savings:
$10,444
Cost:
$11,400
$3,784 103,751 $1,720 208 $4,940 - $3,784
103,751
kWh
$1,720
208
kW-months/year
$4,940
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost