Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1996 |
Principal Product | Billboards |
NAICS | n/a |
SIC | 3317 - Steel Pipe And Tubes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 18 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 1,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $31,558 | 390,094 | kWh | $0.08 |
Electricity Demand | $17,099 | 1,231 | kW-months/year | $13.89 |
Electricity Fees | $4,027 | - | $ | - |
Natural Gas | $3,887 | 669 | MMBtu | $5.81 |
TOTAL ENERGY COSTS | $56,571 | |||
RECOMMENDED SAVINGS* | $25,864 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,444 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $4,940 Cost: - |
- | - | - | - | $4,940 | - |
- - kWh |
- - kW-months/year |
$4,940 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $720 Cost: $300 |
- | - | $720 | 48 | - | - |
- - kWh |
$720 48 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,504 Cost: $11,400 |
$3,784 | 103,751 | $1,720 | 208 | - | - |
$3,784 103,751 kWh |
$1,720 208 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $14,700 Cost: $5,000 |
- | - | - | - | $14,700 | - |
- - kWh |
- - kW-months/year |
$14,700 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,864 Cost: $16,700 |
$3,784 | 103,751 | $2,440 | 256 | $19,640 | - | $3,784 103,751 kWh |
$2,440 256 kW-months/year |
$19,640 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,444 Cost: $11,400 |
$3,784 | 103,751 | $1,720 | 208 | $4,940 | - | $3,784 103,751 kWh |
$1,720 208 kW-months/year |
$4,940 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost |