Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1998 |
Principal Product | hand tools |
NAICS | n/a |
SIC | 3421 - Cutlery |
Sales | $50,000,000-$100,000,000 |
# of Employees | 320 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 5,800,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $605,580 | 18,924,385 | kWh | $0.03 |
Electricity Demand | $276,145 | 24,959 | kW-months/year | $11.06 |
Electricity Fees | $52,903 | - | $ | - |
Natural Gas | $112,056 | 24,259 | MMBtu | $4.62 |
TOTAL ENERGY COSTS | $1,059,478 | |||
RECOMMENDED SAVINGS* | $172,665 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $18,260 Cost: $3,100 |
$17,226 | 538,394 | - | - | $1,034 | - | - | - | - | - | - | - | - | - |
$17,226 538,394 kWh |
- - kW-months/year |
$1,034 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2514 COVER OPEN TANKS |
Savings: $21,415 Cost: $6,174 |
$11,023 | 436,694 | $9,179 | 831 | $1,213 | - | - | - | - | - | - | - | - | - |
$11,023 436,694 kWh |
$9,179 831 kW-months/year |
$1,213 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,874 Cost: $52,766 |
$3,533 | 139,801 | $2,952 | 267 | $389 | - | - | - | - | - | - | - | - | - |
$3,533 139,801 kWh |
$2,952 267 kW-months/year |
$389 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,505 Cost: $3,933 |
$774 | 30,481 | $646 | 58 | $85 | - | - | - | - | - | - | - | - | - |
$774 30,481 kWh |
$646 58 kW-months/year |
$85 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,004 Cost: $413 |
- | - | - | - | - | - | $1,004 | 107 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,004 107 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $16,208 Cost: $38,860 |
- | - | - | - | - | - | - | - | $3,028 | 208,800 | $13,180 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$3,028 208,800 lb |
$13,180 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $2,099 Cost: - |
- | - | - | - | - | - | - | - | $699 | 150,000 | $1,400 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$699 150,000 lb |
$1,400 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $105,300 Cost: $120,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $105,300 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
$105,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $172,665 Cost: $225,246 |
$32,556 | 1,145,370 | $12,777 | 1,156 | $2,721 | - | $1,004 | 107 | $3,727 | 358,800 | $14,580 | - | $105,300 | - | $32,556 1,145,370 kWh |
$12,777 1,156 kW-months/year |
$2,721 - $ |
$1,004 107 MMBtu |
$3,727 358,800 lb |
$14,580 - $ |
$105,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Primary Product |