IAC Assessment: GT0652
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0652
IAC Center Georgia Institute of Technology
Assessment Year 1998
Principal Product Windup clocks
NAICS n/a
SIC 3873 - Watches, Clocks, Watchcases & Parts
Sales $100,000,000-$500,000,000
# of Employees 650
Plant Area (Sq.Ft.) 331,000
Annual Production 12,500,000 Pieces
Production Hrs. Annual 6,000
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $316,734 11,517,585 kWh $0.03
Electricity Demand $338,371 28,160 kW-months/year $12.02
Electricity Fees $55,383 - $ -
Natural Gas $58,932 9,603 MMBtu $6.14
TOTAL ENERGY COSTS $821,462
RECOMMENDED SAVINGS* $74,003 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Fuel Oil #2 Water Disposal Solid Waste (haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Fuel Oil #2 Water Disposal Solid Waste (haz) Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ MMBtu $ Tgal $ lb $ $ $ $
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$9,935
Cost:
-
- - $151,342 13,200 - - $(-73,656) (-682) - - - - $(-15,345) - $(-52,406) - -
-
kWh
$151,342
13,200
kW-months/year
-
-
MMBtu
$(-73,656)
(-682)
MMBtu
-
-
Tgal
-
-
lb
$(-15,345)
-
$
$(-52,406)
-
$
02: 3.4155 METER WASTE WATER Savings:
$6,890
Cost:
$1,000
- - - - - - - - - - - - - - $6,890 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
$6,890
-
$
03: 2.2111 INSTALL STEAM TRAP Savings:
$2,103
Cost:
$2,800
- - - - $2,010 329 - - $93 25,354 - - - - - - -
-
kWh
-
-
kW-months/year
$2,010
329
MMBtu
-
-
MMBtu
$93
25,354
Tgal
-
-
lb
-
-
$
-
-
$
04: 4.4220 UTILIZE OUTSIDE CONTRACTING Savings:
$4,345
Cost:
-
$908 33,118 - - $7,056 1,086 - - - - - - $20,686 - $(-24,305) - $908
33,118
kWh
-
-
kW-months/year
$7,056
1,086
MMBtu
-
-
MMBtu
-
-
Tgal
-
-
lb
$20,686
-
$
$(-24,305)
-
$
05: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$10,000
Cost:
$250
- - - - - - - - - - $10,000 2,694 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
-
-
Tgal
$10,000
2,694
lb
-
-
$
-
-
$
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$3,300
Cost:
-
$3,300 119,871 - - - - - - - - - - - - - - $3,300
119,871
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$37,430
Cost:
$130,994
$12,914 469,519 $24,516 2,040 - - - - - - - - - - - - $12,914
469,519
kWh
$24,516
2,040
kW-months/year
-
-
MMBtu
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$74,003
Cost:
$135,044
$17,122 622,508 $175,858 15,240 $9,066 1,415 $(-73,656) (-682) $93 25,354 $10,000 2,694 $5,341 - $(-69,821) - $17,122
622,508
kWh
$175,858
15,240
kW-months/year
$9,066
1,415
MMBtu
$(-73,656)
(-682)
MMBtu
$93
25,354
Tgal
$10,000
2,694
lb
$5,341
-
$
$(-69,821)
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ MMBtu $ Tgal $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Fuel Oil #2 Water Disposal Solid Waste (haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Fuel Oil #2 Water Disposal Solid Waste (haz) Personnel Changes Administrative Changes