Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2001 |
Principal Product | Circuit Boards |
NAICS | n/a |
SIC | 3672 - Printed Circuit Boards |
Sales | $10,000,000-$50,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 250,000 Pieces |
Production Hrs. Annual | 5,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $18,749 | 604,800 | kWh | $0.03 |
Electricity Demand | $19,634 | 1,823 | kW-months/year | $10.77 |
Electricity Fees | $7,557 | - | $ | - |
Natural Gas | $3,061 | 319 | MMBtu | $9.60 |
TOTAL ENERGY COSTS | $49,001 | |||
RECOMMENDED SAVINGS* | $10,436 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $860 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $6,495 Cost: $2,000 |
- | - | - | - | $6,495 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,495 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,025 Cost: $3,725 |
$981 | 31,654 | $910 | 85 | $134 | - | - | - | - | - | - | - |
$981 31,654 kWh |
$910 85 kW-months/year |
$134 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $845 Cost: $1,450 |
$277 | 8,936 | $514 | 48 | $54 | - | - | - | - | - | - | - |
$277 8,936 kWh |
$514 48 kW-months/year |
$54 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $331 Cost: $310 |
$64 | 2,078 | $30 | 3 | - | - | - | - | $27 | - | $210 | - |
$64 2,078 kWh |
$30 3 kW-months/year |
- - $ |
- - MMBtu |
$27 - $ |
$210 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6241 REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY |
Savings: $15 Cost: - |
$15 | 495 | - | - | - | - | - | - | - | - | - | - |
$15 495 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $75 Cost: - |
$24 | 778 | $46 | 4 | $5 | - | - | - | - | - | - | - |
$24 778 kWh |
$46 4 kW-months/year |
$5 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2222 CONVERT LIQUID HEATERS FROM UNDERFIRING TO IMMERSION OR SUBMERSION HEATING |
Savings: $140 Cost: $800 |
$140 | 4,463 | - | - | - | - | - | - | - | - | - | - |
$140 4,463 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $510 Cost: $225 |
$60 | 1,940 | - | - | - | - | $450 | 47 | - | - | - | - |
$60 1,940 kWh |
- - kW-months/year |
- - $ |
$450 47 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,436 Cost: $8,510 |
$1,561 | 50,344 | $1,500 | 140 | $6,688 | - | $450 | 47 | $27 | - | $210 | - | $1,561 50,344 kWh |
$1,500 140 kW-months/year |
$6,688 - $ |
$450 47 MMBtu |
$27 - $ |
$210 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $860 Cost: $1,450 |
$292 | 9,431 | $514 | 48 | $54 | - | - | - | - | - | - | - | $292 9,431 kWh |
$514 48 kW-months/year |
$54 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Ancillary Material Cost |