Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2002 |
Principal Product | corrugated cardboard |
NAICS | n/a |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 143 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 804,000 Thousand Feet |
Production Hrs. Annual | 7,200 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $120,269 | 4,262,603 | kWh | $0.03 |
Electricity Demand | $144,890 | 9,088 | kW-months/year | $15.94 |
Natural Gas | $221,241 | 44,037 | MMBtu | $5.02 |
TOTAL ENERGY COSTS | $486,400 | |||
RECOMMENDED SAVINGS* | $41,100 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $41,100 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,194 Cost: $6,268 |
$715 | 26,084 | $1,479 | 8 | - | - |
$715 26,084 kWh |
$1,479 8 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,887 Cost: $4,500 |
$974 | 3,517 | $913 | 5 | - | - |
$974 3,517 kWh |
$913 5 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $17,145 Cost: $2,556 |
$8,857 | 327,081 | $8,288 | 45 | - | - |
$8,857 327,081 kWh |
$8,288 45 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,400 Cost: $2,250 |
$1,757 | 64,771 | $1,643 | 9 | - | - |
$1,757 64,771 kWh |
$1,643 9 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $6,705 Cost: - |
- | - | - | - | $6,705 | 1,515 |
- - kWh |
- - kW-months/year |
$6,705 1,515 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $9,769 Cost: $31,236 |
$4,457 | 164,420 | $5,312 | 29 | - | - |
$4,457 164,420 kWh |
$5,312 29 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $41,100 Cost: $46,810 |
$16,760 | 585,873 | $17,635 | 96 | $6,705 | 1,515 | $16,760 585,873 kWh |
$17,635 96 kW-months/year |
$6,705 1,515 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $41,100 Cost: $46,810 |
$16,760 | 585,873 | $17,635 | 96 | $6,705 | 1,515 | $16,760 585,873 kWh |
$17,635 96 kW-months/year |
$6,705 1,515 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |