IAC Assessment: HO0098
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0098
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1995
Principal Product Janitorial Equipment
NAICS n/a
SIC 3499 - Fabricated Metal Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 350
Plant Area (Sq.Ft.) 230,000
Annual Production 485,000 Pieces
Production Hrs. Annual 2,860
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $177,481 1,096,424 kWh $0.16
Fuel Oil #4 $39,215 7,410 MMBtu $5.29
TOTAL ENERGY COSTS $216,696
RECOMMENDED SAVINGS* $20,250 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #4 Electricity Usage Fuel Oil #4
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,000
Cost:
$6,480
$9,000 54,513 - - $9,000
54,513
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$725
Cost:
$1,037
$725 4,103 - - $725
4,103
kWh
-
-
MMBtu
03: 2.1232 KEEP BOILER TUBES CLEAN Savings:
$5,302
Cost:
$2,000
- - $5,302 1,002 -
-
kWh
$5,302
1,002
MMBtu
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$356
Cost:
$800
$356 2,345 - - $356
2,345
kWh
-
-
MMBtu
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,393
Cost:
$900
$1,393 8,792 - - $1,393
8,792
kWh
-
-
MMBtu
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$2,520
Cost:
-
$697 4,396 $1,823 345 $697
4,396
kWh
$1,823
345
MMBtu
07: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$269
Cost:
$338
- - $269 51 -
-
kWh
$269
51
MMBtu
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$685
Cost:
$900
$685 4,396 - - $685
4,396
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$20,250
Cost:
$12,455
$12,856 78,545 $7,394 1,398 $12,856
78,545
kWh
$7,394
1,398
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Fuel Oil #4 Electricity Usage Fuel Oil #4