Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Hofstra Univ. |
---|---|
Assessment Year | 1995 |
Principal Product | Envelopes |
NAICS | n/a |
SIC | 2759 - Commercial Printing, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 200,000,000 Pieces |
Production Hrs. Annual | 4,992 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $350,851 | 2,490,914 | kWh | $0.14 |
Natural Gas | $39,430 | 4,518 | MMBtu | $8.73 |
Fuel Oil #2 | $15,217 | 2,336 | MMBtu | $6.51 |
TOTAL ENERGY COSTS | $405,498 | |||
RECOMMENDED SAVINGS* | $5,955 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,955 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #2 | Electricity Usage | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,584 Cost: $11,286 |
$5,584 | 39,273 | - | - |
$5,584 39,273 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $276 Cost: $365 |
$276 | 2,052 | - | - |
$276 2,052 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $95 Cost: $236 |
- | - | $95 | 15 |
- - kWh |
$95 15 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $5,955 Cost: $11,887 |
$5,860 | 41,325 | $95 | 15 | $5,860 41,325 kWh |
$95 15 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,955 Cost: $11,887 |
$5,860 | 41,325 | $95 | 15 | $5,860 41,325 kWh |
$95 15 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #2 | Electricity Usage | Fuel Oil #2 |