IAC Assessment: HO0128
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0128
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1996
Principal Product Pretzels
NAICS n/a
SIC 2051 - Bread, Cake, And Related Products
Sales $1,000,000-$5,000,000
# of Employees 60
Plant Area (Sq.Ft.) 25,000
Annual Production 5,000,000 Pieces
Production Hrs. Annual 4,160
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $17,485 296,893 kWh $0.06
Electricity Demand $41,077 1,764 kW-months/year $23.29
Electricity Fees $3,134 - $ -
Natural Gas $67,371 8,144 MMBtu $8.27
TOTAL ENERGY COSTS $129,067
RECOMMENDED SAVINGS* $5,545 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,165
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ lb
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$574
Cost:
$827
$228 3,810 $346 15 - - - - $228
3,810
kWh
$346
15
kW-months/year
-
-
MMBtu
-
-
lb
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$391
Cost:
$528
$155 2,638 $236 10 - - - - $155
2,638
kWh
$236
10
kW-months/year
-
-
MMBtu
-
-
lb
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$2,380
Cost:
$740
- - - - $2,380 288 - - -
-
kWh
-
-
kW-months/year
$2,380
288
MMBtu
-
-
lb
04: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$1,000
Cost:
$1,900
- - - - $1,000 120 - - -
-
kWh
-
-
kW-months/year
$1,000
120
MMBtu
-
-
lb
05: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$1,200
Cost:
$100
- - - - - - $1,200 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,200
-
lb
TOTAL RECOMMENDED Savings:
$5,545
Cost:
$4,095
$383 6,448 $582 25 $3,380 408 $1,200 - $383
6,448
kWh
$582
25
kW-months/year
$3,380
408
MMBtu
$1,200
-
lb
TOTAL IMPLEMENTED Savings:
$3,165
Cost:
$3,355
$383 6,448 $582 25 $1,000 120 $1,200 - $383
6,448
kWh
$582
25
kW-months/year
$1,000
120
MMBtu
$1,200
-
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)