IAC Assessment: HO0141
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0141
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1997
Principal Product Sheet metal fabricators
NAICS n/a
SIC 3444 - Sheet Metalwork
Sales $5,000,000-$10,000,000
# of Employees 135
Plant Area (Sq.Ft.) 60,000
Annual Production 1,300,000 Pounds
Production Hrs. Annual 2,860
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $23,076 387,163 kWh $0.06
Electricity Demand $42,860 1,872 kW-months/year $22.90
Electricity Fees $4,772 - $ -
Natural Gas $18,448 1,957 MMBtu $9.43
TOTAL ENERGY COSTS $89,156
RECOMMENDED SAVINGS* $143,736 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,232
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Water Disposal Solid Waste (non-haz) Personnel Changes
$ kWh $ kW-months/year $ Tgal $ lb $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$7,534
Cost:
$16,787
$2,866 47,773 $4,668 204 - - - - - - $2,866
47,773
kWh
$4,668
204
kW-months/year
-
-
Tgal
-
-
lb
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$798
Cost:
$3,720
$798 13,189 - - - - - - - - $798
13,189
kWh
-
-
kW-months/year
-
-
Tgal
-
-
lb
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,226
Cost:
$400
$471 7,913 $755 33 - - - - - - $471
7,913
kWh
$755
33
kW-months/year
-
-
Tgal
-
-
lb
-
-
$
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,306
Cost:
$200
$505 8,499 $801 35 - - - - - - $505
8,499
kWh
$801
35
kW-months/year
-
-
Tgal
-
-
lb
-
-
$
05: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$2,232
Cost:
$1,000
- - - - $2,232 603,424 - - - - -
-
kWh
-
-
kW-months/year
$2,232
603,424
Tgal
-
-
lb
-
-
$
06: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$5,640
Cost:
-
- - - - - - $5,640 - - - -
-
kWh
-
-
kW-months/year
-
-
Tgal
$5,640
-
lb
-
-
$
07: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$75,000
Cost:
$40,000
- - - - - - - - $75,000 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
lb
$75,000
-
$
08: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS Savings:
$50,000
Cost:
$50,000
- - - - - - - - $50,000 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
lb
$50,000
-
$
TOTAL RECOMMENDED Savings:
$143,736
Cost:
$112,107
$4,640 77,374 $6,224 272 $2,232 603,424 $5,640 - $125,000 - $4,640
77,374
kWh
$6,224
272
kW-months/year
$2,232
603,424
Tgal
$5,640
-
lb
$125,000
-
$
TOTAL IMPLEMENTED Savings:
$2,232
Cost:
$1,000
- - - - $2,232 603,424 - - - - -
-
kWh
-
-
kW-months/year
$2,232
603,424
Tgal
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ Tgal $ lb $ $
Electricity Usage Electricity Demand Water Disposal Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Water Disposal Solid Waste (non-haz) Personnel Changes