IAC Assessment: HO0145
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0145
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1997
Principal Product Vibration control products
NAICS n/a
SIC 3061 - Mechanical Rubber Goods
Sales $10,000,000-$50,000,000
# of Employees 175
Plant Area (Sq.Ft.) 80,000
Annual Production 1,000,000 Pounds
Production Hrs. Annual 2,210
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $82,155 908,558 kWh $0.09
Electricity Demand $55,744 4,855 kW-months/year $11.48
Electricity Fees $9,912 - $ -
Natural Gas $74,250 8,937 MMBtu $8.31
TOTAL ENERGY COSTS $229,861
RECOMMENDED SAVINGS* $24,332 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $661
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ gal $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,073
Cost:
$6,276
$1,246 13,775 $827 72 - - - - - - $1,246
13,775
kWh
$827
72
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$327
Cost:
$1,433
$327 3,517 - - - - - - - - $327
3,517
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$661
Cost:
$500
$392 4,396 $269 23 - - - - - - $392
4,396
kWh
$269
23
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$9,805
Cost:
$17,760
- - - - $9,805 1,181 - - - - -
-
kWh
-
-
kW-months/year
$9,805
1,181
MMBtu
-
-
gal
-
-
$
05: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$1,170
Cost:
$500
- - - - - - $1,170 78 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,170
78
gal
-
-
$
06: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$10,296
Cost:
$10,000
- - - - - - - - $10,296 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$10,296
-
$
TOTAL RECOMMENDED Savings:
$24,332
Cost:
$36,469
$1,965 21,688 $1,096 95 $9,805 1,181 $1,170 78 $10,296 - $1,965
21,688
kWh
$1,096
95
kW-months/year
$9,805
1,181
MMBtu
$1,170
78
gal
$10,296
-
$
TOTAL IMPLEMENTED Savings:
$661
Cost:
$500
$392 4,396 $269 23 - - - - - - $392
4,396
kWh
$269
23
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes