IAC Assessment: HO0181
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0181
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1998
Principal Product Anodizing
NAICS n/a
SIC 3479 - Metal Coating And Allied Services
Sales $1,000,000-$5,000,000
# of Employees 49
Plant Area (Sq.Ft.) 12,000
Annual Production 5,500 Thousand Feet
Production Hrs. Annual 2,574
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $29,173 550,703 kWh $0.05
Electricity Demand $122,324 5,665 kW-months/year $21.59
Electricity Fees $(-1,341) - $ -
Natural Gas $18,957 2,072 MMBtu $9.15
Fuel Oil #2 $47,363 8,131 MMBtu $5.82
TOTAL ENERGY COSTS $216,476
RECOMMENDED SAVINGS* $105,519 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $14,913
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Water Consumption Electricity Usage Electricity Demand Natural Gas Administrative Changes Water Consumption
$ kWh $ kW-months/year $ MMBtu $ $ $ Tgal
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,163
Cost:
$10,944
$868 14,068 $1,295 60 - - - - - - $868
14,068
kWh
$1,295
60
kW-months/year
-
-
MMBtu
-
-
$
-
-
Tgal
02: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$88,443
Cost:
$310,000
$29,187 550,996 $122,286 5,664 $(-43,839) (-5,697) $(-19,191) - - - $29,187
550,996
kWh
$122,286
5,664
kW-months/year
$(-43,839)
(-5,697)
MMBtu
$(-19,191)
-
$
-
-
Tgal
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$532
Cost:
$325
- - - - $532 58 - - - - -
-
kWh
-
-
kW-months/year
$532
58
MMBtu
-
-
$
-
-
Tgal
04: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,232
Cost:
$1,008
- - - - $1,232 187 - - - - -
-
kWh
-
-
kW-months/year
$1,232
187
MMBtu
-
-
$
-
-
Tgal
05: 2.2123 INSULATE FEEDWATER TANK Savings:
$227
Cost:
$72
- - - - $227 15 - - - - -
-
kWh
-
-
kW-months/year
$227
15
MMBtu
-
-
$
-
-
Tgal
06: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$12,922
Cost:
$250
- - - - - - - - $12,922 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$12,922
-
Tgal
TOTAL RECOMMENDED Savings:
$105,519
Cost:
$322,599
$30,055 565,064 $123,581 5,724 $(-41,848) (-5,437) $(-19,191) - $12,922 - $30,055
565,064
kWh
$123,581
5,724
kW-months/year
$(-41,848)
(-5,437)
MMBtu
$(-19,191)
-
$
$12,922
-
Tgal
TOTAL IMPLEMENTED Savings:
$14,913
Cost:
$1,655
- - - - $1,991 260 - - $12,922 - -
-
kWh
-
-
kW-months/year
$1,991
260
MMBtu
-
-
$
$12,922
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ Tgal
Electricity Usage Electricity Demand Natural Gas Administrative Changes Water Consumption Electricity Usage Electricity Demand Natural Gas Administrative Changes Water Consumption