Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Hofstra Univ. |
---|---|
Assessment Year | 1999 |
Principal Product | Knobs |
NAICS | n/a |
SIC | 3679 - Electronic Components, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 20,000 |
Annual Production | 4,500,000 Pieces |
Production Hrs. Annual | 2,075 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,525 | 842,321 | kWh | $0.08 |
Electricity Demand | $30,001 | 4,456 | kW-months/year | $6.73 |
Electricity Fees | $6,520 | - | $ | - |
Natural Gas | $14,305 | 1,658 | MMBtu | $8.63 |
TOTAL ENERGY COSTS | $120,351 | |||
RECOMMENDED SAVINGS* | $31,925 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,112 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,422 Cost: $14,000 |
$3,033 | 36,928 | $1,389 | 206 | - | - | - | - |
$3,033 36,928 kWh |
$1,389 206 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,100 Cost: - |
$1,100 | 13,482 | - | - | - | - | - | - |
$1,100 13,482 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $234 Cost: $398 |
$234 | 2,931 | - | - | - | - | - | - |
$234 2,931 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS |
Savings: $6,813 Cost: $27,000 |
- | - | - | - | $6,813 | - | - | - |
- - kWh |
- - kW-months/year |
$6,813 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,667 Cost: $400 |
$5,667 | 68,581 | - | - | - | - | - | - |
$5,667 68,581 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $2,661 Cost: $500 |
$2,661 | 32,239 | - | - | - | - | - | - |
$2,661 32,239 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $4,800 Cost: $5,000 |
- | - | - | - | - | - | $4,800 | - |
- - kWh |
- - kW-months/year |
- - $ |
$4,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $6,228 Cost: $10,000 |
- | - | - | - | - | - | $6,228 | - |
- - kWh |
- - kW-months/year |
- - $ |
$6,228 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $31,925 Cost: $57,298 |
$12,695 | 154,161 | $1,389 | 206 | $6,813 | - | $11,028 | - | $12,695 154,161 kWh |
$1,389 206 kW-months/year |
$6,813 - $ |
$11,028 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,112 Cost: $30,298 |
$12,695 | 154,161 | $1,389 | 206 | - | - | $11,028 | - | $12,695 154,161 kWh |
$1,389 206 kW-months/year |
- - $ |
$11,028 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost |