Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Hofstra Univ. |
---|---|
Assessment Year | 1999 |
Principal Product | Metal Stampings |
NAICS | n/a |
SIC | 3469 - Metal Stampings, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 68 |
Plant Area (Sq.Ft.) | 95,000 |
Annual Production | 100,000 Pounds |
Production Hrs. Annual | 2,125 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $71,502 | 828,253 | kWh | $0.09 |
Electricity Demand | $48,195 | 5,333 | kW-months/year | $9.04 |
Electricity Fees | $1,905 | - | $ | - |
Natural Gas | $45,359 | 7,076 | MMBtu | $6.41 |
TOTAL ENERGY COSTS | $166,961 | |||
RECOMMENDED SAVINGS* | $36,469 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,352 Cost: $47,121 |
$9,650 | 111,665 | $5,702 | 631 | - | - | - | - |
$9,650 111,665 kWh |
$5,702 631 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,578 Cost: $1,600 |
$2,578 | 29,894 | - | - | - | - | - | - |
$2,578 29,894 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,190 Cost: $800 |
$1,190 | 13,775 | - | - | - | - | - | - |
$1,190 13,775 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $610 Cost: - |
$610 | 7,034 | - | - | - | - | - | - |
$610 7,034 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $205 Cost: $500 |
$205 | 2,345 | - | - | - | - | - | - |
$205 2,345 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.512 CONDENSE OPERATION INTO ONE BUILDING |
Savings: $3,938 Cost: $8,000 |
$2,474 | 28,722 | $1,464 | 162 | - | - | - | - |
$2,474 28,722 kWh |
$1,464 162 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2223 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF |
Savings: $4,536 Cost: $700 |
- | - | - | - | $4,536 | 708 | - | - |
- - kWh |
- - kW-months/year |
$4,536 708 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $2,340 Cost: $630 |
- | - | - | - | - | - | $2,340 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,340 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.632 CHANGE OPERATING CONDITIONS |
Savings: $5,720 Cost: $27,500 |
- | - | - | - | - | - | $5,720 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$5,720 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $36,469 Cost: $86,851 |
$16,707 | 193,435 | $7,166 | 793 | $4,536 | 708 | $8,060 | - | $16,707 193,435 kWh |
$7,166 793 kW-months/year |
$4,536 708 MMBtu |
$8,060 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost |