Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 1991 |
Principal Product | SPORT SOCKS |
NAICS | n/a |
SIC | 2252 - Hosiery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 600,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $104,562 | 2,428,781 | kWh | $0.04 |
Natural Gas | $72,698 | 20,636 | MMBtu | $3.52 |
TOTAL ENERGY COSTS | $177,260 | |||
RECOMMENDED SAVINGS* | $11,183 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,183 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7312 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE |
Savings: $6,926 Cost: $5,950 |
- | - | $6,926 | 1,966 | - | - |
- - kWh |
$6,926 1,966 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,004 Cost: - |
$3,988 | 94,080 | - | - | $(-984) | - |
$3,988 94,080 kWh |
- - MMBtu |
$(-984) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $679 Cost: $2,792 |
$679 | 15,826 | - | - | - | - |
$679 15,826 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $574 Cost: $450 |
- | - | $574 | 163 | - | - |
- - kWh |
$574 163 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,183 Cost: $9,192 |
$4,667 | 109,906 | $7,500 | 2,129 | $(-984) | - | $4,667 109,906 kWh |
$7,500 2,129 MMBtu |
$(-984) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,183 Cost: $9,192 |
$4,667 | 109,906 | $7,500 | 2,129 | $(-984) | - | $4,667 109,906 kWh |
$7,500 2,129 MMBtu |
$(-984) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |