Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 1992 |
Principal Product | PIZZA TOPPINGS |
NAICS | n/a |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 21,000,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $141,074 | 2,591,442 | kWh | $0.05 |
Natural Gas | $134,666 | 32,058 | MMBtu | $4.20 |
TOTAL ENERGY COSTS | $275,740 | |||
RECOMMENDED SAVINGS* | $13,802 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,217 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2425 USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER |
Savings: $7,666 Cost: $15 |
- | - | $7,666 | 1,825 | - | - |
- - kWh |
$7,666 1,825 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $486 Cost: $714 |
- | - | $486 | 116 | - | - |
- - kWh |
$486 116 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $1,634 Cost: $496 |
- | - | $1,634 | 389 | - | - |
- - kWh |
$1,634 389 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $736 Cost: $4,500 |
$736 | 13,189 | - | - | - | - |
$736 13,189 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,465 Cost: $779 |
$3,277 | 59,203 | - | - | $(-812) | - |
$3,277 59,203 kWh |
- - MMBtu |
$(-812) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $815 Cost: $1,080 |
$815 | 14,654 | - | - | - | - |
$815 14,654 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,802 Cost: $7,584 |
$4,828 | 87,046 | $9,786 | 2,330 | $(-812) | - | $4,828 87,046 kWh |
$9,786 2,330 MMBtu |
$(-812) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,217 Cost: $5,595 |
$1,551 | 27,843 | $7,666 | 1,825 | - | - | $1,551 27,843 kWh |
$7,666 1,825 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |