Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 1993 |
Principal Product | STEEL FORGINGS |
NAICS | n/a |
SIC | 3462 - Iron And Steel Forgings |
Sales | $5,000,000-$10,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 10,200,000 Pounds |
Production Hrs. Annual | 3,473 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $207,807 | 2,772,567 | kWh | $0.07 |
Natural Gas | $301,126 | 69,265 | MMBtu | $4.35 |
Fuel Oil #2 | $7,870 | 2,141 | MMBtu | $3.68 |
TOTAL ENERGY COSTS | $516,803 | |||
RECOMMENDED SAVINGS* | $36,543 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $30,399 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $21,047 Cost: $82,940 |
$21,047 | 280,774 | - | - | - | - |
$21,047 280,774 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4223 INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM |
Savings: $5,451 Cost: $3,230 |
$5,451 | 72,685 | - | - | - | - |
$5,451 72,685 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,186 Cost: $100 |
$2,186 | 29,308 | - | - | - | - |
$2,186 29,308 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $2,421 Cost: $685 |
$2,421 | 32,239 | - | - | - | - |
$2,421 32,239 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $402 Cost: $925 |
$402 | 5,275 | - | - | - | - |
$402 5,275 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $2,719 Cost: $10,200 |
- | - | $2,719 | 625 | - | - |
- - kWh |
$2,719 625 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $165 Cost: - |
$461 | 6,155 | - | - | $(-296) | - |
$461 6,155 kWh |
- - MMBtu |
$(-296) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $528 Cost: $840 |
$528 | 7,034 | - | - | - | - |
$528 7,034 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $473 Cost: $665 |
$473 | 6,448 | - | - | - | - |
$473 6,448 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $556 Cost: $215 |
$556 | 7,327 | - | - | - | - |
$556 7,327 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $595 Cost: $1,350 |
$253 | 3,224 | $342 | 79 | - | - |
$253 3,224 kWh |
$342 79 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $36,543 Cost: $101,150 |
$33,778 | 450,469 | $3,061 | 704 | $(-296) | - | $33,778 450,469 kWh |
$3,061 704 MMBtu |
$(-296) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $30,399 Cost: $97,080 |
$27,338 | 364,595 | $3,061 | 704 | - | - | $27,338 364,595 kWh |
$3,061 704 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |