Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 1996 |
Principal Product | Sign Letters |
NAICS | n/a |
SIC | 3079 - |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 1,400,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $82,634 | 3,180,246 | kWh | $0.03 |
Electricity Demand | $83,525 | 11,808 | kW-months/year | $7.07 |
Electricity Fees | $3,803 | - | $ | - |
Natural Gas | $9,060 | 2,250 | MMBtu | $4.03 |
TOTAL ENERGY COSTS | $184,564 | |||
RECOMMENDED SAVINGS* | $6,335 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,893 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (haz) | Electricity Usage | Electricity Demand | Solid Waste (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $2,323 Cost: - |
- | - | $2,323 | 328 | - | - |
- - kWh |
$2,323 328 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,297 Cost: $63 |
$838 | 32,239 | $459 | 65 | - | - |
$838 32,239 kWh |
$459 65 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $350 Cost: $262 |
$231 | 8,792 | $119 | 17 | - | - |
$231 8,792 kWh |
$119 17 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $900 Cost: $1,362 |
$526 | 20,223 | $374 | 53 | - | - |
$526 20,223 kWh |
$374 53 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $346 Cost: $444 |
$212 | 8,206 | $134 | 36 | - | - |
$212 8,206 kWh |
$134 36 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $466 Cost: $92 |
$177 | 6,741 | $289 | 41 | - | - |
$177 6,741 kWh |
$289 41 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.1161 ELIMINATE/REDUCE AN OPERATION |
Savings: $653 Cost: $574 |
- | - | - | - | $653 | 528 |
- - kWh |
- - kW-months/year |
$653 528 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $6,335 Cost: $2,797 |
$1,984 | 76,201 | $3,698 | 540 | $653 | 528 | $1,984 76,201 kWh |
$3,698 540 kW-months/year |
$653 528 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,893 Cost: $2,131 |
$1,807 | 69,460 | $1,086 | 171 | - | - | $1,807 69,460 kWh |
$1,086 171 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (haz) | Electricity Usage | Electricity Demand | Solid Waste (haz) |