IAC Assessment: IA0173
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0173
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 1997
Principal Product Industrial Laminates
NAICS n/a
SIC 3083 - Laminated Plastics Plate & Sheet
Sales $10,000,000-$50,000,000
# of Employees 125
Plant Area (Sq.Ft.) 113,000
Annual Production 12,000,000 Pounds
Production Hrs. Annual 6,000
Location (State) IA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $130,694 5,107,855 kWh $0.03
Electricity Demand $71,838 11,076 kW-months/year $6.49
Natural Gas $380,414 146,970 MMBtu $2.59
TOTAL ENERGY COSTS $594,009
RECOMMENDED SAVINGS* $115,024 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,325
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Primary Raw Material Water Consumption Electricity Usage Electricity Demand Natural Gas Primary Raw Material Water Consumption
$ kWh $ kW-months/year $ MMBtu $ $ $ Tgal
01: 3.4115 RECOVER AND REUSE COOLING WATER Savings:
$99,165
Cost:
$105,000
$(-3,556) (-136,870) $(-2,726) (-428) - - - - $105,447 - $(-3,556)
(-136,870)
kWh
$(-2,726)
(-428)
kW-months/year
-
-
MMBtu
-
-
$
$105,447
-
Tgal
02: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING Savings:
$5,284
Cost:
$4,100
$883 33,998 $1,239 161 $3,162 1,221 - - - - $883
33,998
kWh
$1,239
161
kW-months/year
$3,162
1,221
MMBtu
-
-
$
-
-
Tgal
03: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$4,119
Cost:
$5,200
$2,668 102,579 $1,451 228 - - - - - - $2,668
102,579
kWh
$1,451
228
kW-months/year
-
-
MMBtu
-
-
$
-
-
Tgal
04: 3.8121 COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES Savings:
$4,250
Cost:
$6,300
- - - - - - $4,250 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$4,250
-
$
-
-
Tgal
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$475
Cost:
$592
$319 12,309 $156 24 - - - - - - $319
12,309
kWh
$156
24
kW-months/year
-
-
MMBtu
-
-
$
-
-
Tgal
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$804
Cost:
$1,705
$537 20,516 $267 42 - - - - - - $537
20,516
kWh
$267
42
kW-months/year
-
-
MMBtu
-
-
$
-
-
Tgal
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$488
Cost:
$538
$320 12,309 $168 26 - - - - - - $320
12,309
kWh
$168
26
kW-months/year
-
-
MMBtu
-
-
$
-
-
Tgal
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$325
Cost:
$139
$218 8,499 $107 17 - - - - - - $218
8,499
kWh
$107
17
kW-months/year
-
-
MMBtu
-
-
$
-
-
Tgal
09: 2.2511 INSULATE BARE EQUIPMENT Savings:
$114
Cost:
$176
- - - - $114 44 - - - - -
-
kWh
-
-
kW-months/year
$114
44
MMBtu
-
-
$
-
-
Tgal
TOTAL RECOMMENDED Savings:
$115,024
Cost:
$123,750
$1,389 53,340 $662 70 $3,276 1,265 $4,250 - $105,447 - $1,389
53,340
kWh
$662
70
kW-months/year
$3,276
1,265
MMBtu
$4,250
-
$
$105,447
-
Tgal
TOTAL IMPLEMENTED Savings:
$6,325
Cost:
$8,350
$4,062 156,212 $2,149 337 $114 44 - - - - $4,062
156,212
kWh
$2,149
337
kW-months/year
$114
44
MMBtu
-
-
$
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ Tgal
Electricity Usage Electricity Demand Natural Gas Primary Raw Material Water Consumption Electricity Usage Electricity Demand Natural Gas Primary Raw Material Water Consumption