IAC Assessment: IA0264
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0264
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 2001
Principal Product EPS, wooden pallets
NAICS n/a
SIC 2448 - Wood Pallets And Skids
Sales $10,000,000-$50,000,000
# of Employees 224
Plant Area (Sq.Ft.) 297,280
Annual Production 4,000,000 Pounds
Production Hrs. Annual 6,240
Location (State) IA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $217,254 4,896,681 kWh $0.04
Electricity Demand $70,186 12,756 kW-months/year $5.50
Natural Gas $425,708 95,872 MMBtu $4.44
TOTAL ENERGY COSTS $715,634
RECOMMENDED SAVINGS* $547,437 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,489
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,722
Cost:
$173
$3,308 111,365 $2,414 217 - - - - $3,308
111,365
kWh
$2,414
217
kW-months/year
-
-
$
-
-
$
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$4,073
Cost:
$780
$2,326 78,318 $1,747 157 - - - - $2,326
78,318
kWh
$1,747
157
kW-months/year
-
-
$
-
-
$
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$3,730
Cost:
$44
$2,061 69,381 $1,669 150 - - - - $2,061
69,381
kWh
$1,669
150
kW-months/year
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,676
Cost:
-
$3,151 106,106 $2,525 227 - - - - $3,151
106,106
kWh
$2,525
227
kW-months/year
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,239
Cost:
$5,199
$1,171 39,442 $1,068 96 - - - - $1,171
39,442
kWh
$1,068
96
kW-months/year
-
-
$
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$328
Cost:
$599
$328 11,059 - - - - - - $328
11,059
kWh
-
-
kW-months/year
-
-
$
-
-
$
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,091
Cost:
-
$624 21,005 $467 42 - - - - $624
21,005
kWh
$467
42
kW-months/year
-
-
$
-
-
$
08: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$303,062
Cost:
$2,050
- - - - - - $303,062 - -
-
kWh
-
-
kW-months/year
-
-
$
$303,062
-
$
09: 4.423 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$177,056
Cost:
$100,000
$(-830) (-27,930) - - $68,640 - $109,246 - $(-830)
(-27,930)
kWh
-
-
kW-months/year
$68,640
-
$
$109,246
-
$
10: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE Savings:
$44,460
Cost:
$8,000
- - - - $(-15,600) - $60,060 - -
-
kWh
-
-
kW-months/year
$(-15,600)
-
$
$60,060
-
$
TOTAL RECOMMENDED Savings:
$547,437
Cost:
$116,845
$12,139 408,746 $9,890 889 $53,040 - $472,368 - $12,139
408,746
kWh
$9,890
889
kW-months/year
$53,040
-
$
$472,368
-
$
TOTAL IMPLEMENTED Savings:
$12,489
Cost:
$173
$7,083 238,476 $5,406 486 - - - - $7,083
238,476
kWh
$5,406
486
kW-months/year
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost