Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2001 |
Principal Product | coated paper products |
NAICS | n/a |
SIC | 2672 - Paper Coated And Laminated, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 190 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 2,704,000 Thousand Feet |
Production Hrs. Annual | 8,640 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $507,083 | 17,348,854 | kWh | $0.03 |
Electricity Demand | $215,842 | 30,384 | kW-months/year | $7.10 |
Natural Gas | $1,191,468 | 335,794 | MMBtu | $3.55 |
TOTAL ENERGY COSTS | $1,970,519 | |||
RECOMMENDED SAVINGS* | $493,639 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $264,205 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $26,215 Cost: $35,700 |
- | - | - | - | $26,215 | 7,242 | - | - | - | - |
- - kWh |
- - kW-months/year |
$26,215 7,242 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7314 REDUCE VENTILATION AIR |
Savings: $12,703 Cost: $5,038 |
$2,664 | 91,232 | $812 | 125 | $9,227 | 2,549 | - | - | - | - |
$2,664 91,232 kWh |
$812 125 kW-months/year |
$9,227 2,549 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $8,737 Cost: - |
$6,673 | 228,543 | $2,064 | 318 | - | - | - | - | - | - |
$6,673 228,543 kWh |
$2,064 318 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,175 Cost: $11,846 |
$5,059 | 173,268 | $2,116 | 326 | - | - | - | - | - | - |
$5,059 173,268 kWh |
$2,116 326 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,933 Cost: - |
$5,298 | 181,440 | $1,635 | 252 | - | - | - | - | - | - |
$5,298 181,440 kWh |
$1,635 252 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,034 Cost: $1,663 |
$2,034 | 69,652 | - | - | - | - | - | - | - | - |
$2,034 69,652 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,804 Cost: $5,398 |
$1,804 | 61,769 | - | - | - | - | - | - | - | - |
$1,804 61,769 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING |
Savings: $6,440 Cost: $3,410 |
- | - | - | - | $6,440 | 1,779 | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,440 1,779 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,027 Cost: $518 |
$7,659 | 262,308 | $2,368 | 365 | - | - | - | - | - | - |
$7,659 262,308 kWh |
$2,368 365 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,165 Cost: $585 |
$2,419 | 82,828 | $746 | 115 | - | - | - | - | - | - |
$2,419 82,828 kWh |
$746 115 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,767 Cost: $2,000 |
- | - | - | - | $1,767 | 488 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,767 488 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $123,691 Cost: $50,000 |
$(-787) | (-26,943) | $(-3,922) | (-604) | - | - | $128,400 | 267,500 | - | - |
$(-787) (-26,943) kWh |
$(-3,922) (-604) kW-months/year |
- - MMBtu |
$128,400 267,500 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 4.453 RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION |
Savings: $231,300 Cost: - |
- | - | - | - | - | - | - | - | $231,300 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$231,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 4.322 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL |
Savings: $51,648 Cost: $32,000 |
- | - | - | - | - | - | $24,000 | 960,000 | $27,648 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$24,000 960,000 lb |
$27,648 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $493,639 Cost: $148,158 |
$32,823 | 1,124,097 | $5,819 | 897 | $43,649 | 12,058 | $152,400 | 1,227,500 | $258,948 | - | $32,823 1,124,097 kWh |
$5,819 897 kW-months/year |
$43,649 12,058 MMBtu |
$152,400 1,227,500 lb |
$258,948 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $264,205 Cost: $16,612 |
$23,844 | 816,599 | $7,294 | 1,124 | $1,767 | 488 | - | - | $231,300 | - | $23,844 816,599 kWh |
$7,294 1,124 kW-months/year |
$1,767 488 MMBtu |
- - lb |
$231,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes |