Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2002 |
Principal Product | precooked meat products |
NAICS | n/a |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $100,000,000-$500,000,000 |
# of Employees | 374 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 7,332,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $521,569 | 19,323,480 | kWh | $0.03 |
Electricity Demand | $150,560 | 33,140 | kW-months/year | $4.54 |
Natural Gas | $545,562 | 112,640 | MMBtu | $4.84 |
TOTAL ENERGY COSTS | $1,377,453 | |||
RECOMMENDED SAVINGS* | $29,855 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,510 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,396 Cost: $581 |
$1,012 | 50,110 | $384 | 96 | - | - | - | - | - | - |
$1,012 50,110 kWh |
$384 96 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $999 Cost: $241 |
$725 | 35,871 | $274 | 68 | - | - | - | - | - | - |
$725 35,871 kWh |
$274 68 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $418 Cost: $16 |
$303 | 14,976 | $115 | 29 | - | - | - | - | - | - |
$303 14,976 kWh |
$115 29 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $1,463 Cost: - |
- | - | - | - | $307 | 63 | $875 | 169,561 | $281 | - |
- - kWh |
- - kW-months/year |
$307 63 MMBtu |
$875 169,561 Tgal |
$281 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $12,482 Cost: - |
$9,400 | 465,346 | $3,082 | 770 | - | - | - | - | - | - |
$9,400 465,346 kWh |
$3,082 770 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,464 Cost: $1,663 |
$1,464 | 72,481 | - | - | - | - | - | - | - | - |
$1,464 72,481 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,844 Cost: $13,381 |
$2,158 | 106,856 | $686 | 172 | - | - | - | - | - | - |
$2,158 106,856 kWh |
$686 172 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,670 Cost: - |
$2,027 | 100,339 | $643 | 161 | - | - | - | - | - | - |
$2,027 100,339 kWh |
$643 161 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,312 Cost: $1,500 |
- | - | - | - | $1,312 | 271 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,312 271 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $2,212 Cost: $1,500 |
- | - | - | - | $2,212 | 457 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,212 457 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $1,752 Cost: $500 |
- | - | - | - | $1,752 | 362 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,752 362 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $843 Cost: $326 |
- | - | - | - | $843 | 174 | - | - | - | - |
- - kWh |
- - kW-months/year |
$843 174 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,855 Cost: $19,708 |
$17,089 | 845,979 | $5,184 | 1,296 | $6,426 | 1,327 | $875 | 169,561 | $281 | - | $17,089 845,979 kWh |
$5,184 1,296 kW-months/year |
$6,426 1,327 MMBtu |
$875 169,561 Tgal |
$281 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,510 Cost: $18,029 |
$15,322 | 758,522 | $5,069 | 1,267 | $6,119 | 1,264 | - | - | - | - | $15,322 758,522 kWh |
$5,069 1,267 kW-months/year |
$6,119 1,264 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption |