Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2006 |
Principal Product | Electric Utility Equipment |
NAICS | 333923 - Overhead Traveling Crane, Hoist, and Monorail System Manufacturing |
SIC | 3531 - Construction Machinery |
Sales | $50,000,000-$100,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 135,000 |
Annual Production | 2,254 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $213,318 | 6,799,448 | kWh | $0.03 |
Electricity Demand | $75,536 | 18,552 | kW-months/year | $4.07 |
Natural Gas | $88,807 | 11,034 | MMBtu | $8.05 |
TOTAL ENERGY COSTS | $377,661 | |||
RECOMMENDED SAVINGS* | $66,792 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $65,513 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,190 Cost: $4,918 |
$3,472 | 110,601 | $718 | 177 | - | - |
$3,472 110,601 kWh |
$718 177 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,183 Cost: $6,385 |
$1,639 | 52,198 | $544 | 135 | - | - |
$1,639 52,198 kWh |
$544 135 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,587 Cost: $3,234 |
$2,587 | 82,391 | - | - | - | - |
$2,587 82,391 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $2,069 Cost: $1,000 |
$2,069 | 65,894 | - | - | - | - |
$2,069 65,894 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,869 Cost: $480 |
$3,205 | 102,063 | $664 | 163 | - | - |
$3,205 102,063 kWh |
$664 163 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,922 Cost: $52 |
$2,422 | 77,126 | $500 | 124 | - | - |
$2,422 77,126 kWh |
$500 124 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,279 Cost: $1,972 |
$1,092 | 28,798 | $187 | 46 | - | - |
$1,092 28,798 kWh |
$187 46 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING |
Savings: $47,693 Cost: $45,600 |
$(-1,878) | (-57,754) | $(-388) | (-96) | $49,959 | 6,206 |
$(-1,878) (-57,754) kWh |
$(-388) (-96) kW-months/year |
$49,959 6,206 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $66,792 Cost: $63,641 |
$14,608 | 461,317 | $2,225 | 549 | $49,959 | 6,206 | $14,608 461,317 kWh |
$2,225 549 kW-months/year |
$49,959 6,206 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $65,513 Cost: $61,669 |
$13,516 | 432,519 | $2,038 | 503 | $49,959 | 6,206 | $13,516 432,519 kWh |
$2,038 503 kW-months/year |
$49,959 6,206 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |