Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2015 |
Principal Product | Service Vehicles |
NAICS | 336211 - Motor Vehicle Body Manufacturing |
SIC | 3713 - Truck And Bus Bodies |
Sales | $100,000,000-$500,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 325,000 |
Annual Production | 3,300 Pieces |
Production Hrs. Annual | 5,100 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $272,108 | 4,972,529 | kWh | $0.05 |
Electricity Demand | $173,035 | 9,622 | kW-months/year | $17.98 |
Electricity Fees | $13,661 | - | $ | - |
Natural Gas | $157,345 | 39,277 | MMBtu | $4.01 |
TOTAL ENERGY COSTS | $616,149 | |||
RECOMMENDED SAVINGS* | $28,101 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,210 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $9,857 Cost: $19,775 |
$2,709 | 49,440 | $3,770 | 206 | $3,378 | 843 |
$2,709 49,440 kWh |
$3,770 206 kW-months/year |
$3,378 843 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,005 Cost: $1,049 |
$3,361 | 61,329 | $2,644 | 144 | - | - |
$3,361 61,329 kWh |
$2,644 144 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,225 Cost: $7,848 |
$1,684 | 30,681 | $541 | 31 | - | - |
$1,684 30,681 kWh |
$541 31 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $2,136 Cost: $210 |
$2,136 | 38,984 | - | - | - | - |
$2,136 38,984 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,294 Cost: $2,575 |
- | - | - | - | $2,294 | 572 |
- - kWh |
- - kW-months/year |
$2,294 572 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,994 Cost: $4,066 |
$2,236 | 40,800 | $1,758 | 96 | - | - |
$2,236 40,800 kWh |
$1,758 96 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $993 Cost: $1,342 |
$553 | 10,098 | $440 | 24 | - | - |
$553 10,098 kWh |
$440 24 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $597 Cost: $2,226 |
$597 | 10,891 | - | - | - | - |
$597 10,891 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,101 Cost: $39,091 |
$13,276 | 242,223 | $9,153 | 501 | $5,672 | 1,415 | $13,276 242,223 kWh |
$9,153 501 kW-months/year |
$5,672 1,415 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,210 Cost: $34,290 |
$12,679 | 231,332 | $9,153 | 501 | $3,378 | 843 | $12,679 231,332 kWh |
$9,153 501 kW-months/year |
$3,378 843 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |