Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2001 |
Principal Product | Point of Purchase Displays |
NAICS | n/a |
SIC | 3993 - Signs And Advertising Specialities |
Sales | $10,000,000-$50,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 45,000 Pieces |
Production Hrs. Annual | 4,290 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $30,113 | 828,083 | kWh | $0.04 |
Electricity Demand | $36,433 | 2,964 | kW-months/year | $12.29 |
Electricity Fees | $7,732 | - | $ | - |
Natural Gas | $76,816 | 12,805 | MMBtu | $6.00 |
TOTAL ENERGY COSTS | $162,854 | |||
RECOMMENDED SAVINGS* | $77,367 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,749 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,749 Cost: $1,150 |
$2,429 | 67,472 | $2,320 | 189 | - | - | - | - | - | - | - | - |
$2,429 67,472 kWh |
$2,320 189 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $3,491 Cost: $10,553 |
$3,012 | 83,660 | $479 | 39 | - | - | - | - | - | - | - | - |
$3,012 83,660 kWh |
$479 39 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $737 Cost: - |
- | - | $737 | 5 | - | - | - | - | - | - | - | - |
- - kWh |
$737 5 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,197 Cost: - |
- | - | $2,197 | 15 | - | - | - | - | - | - | - | - |
- - kWh |
$2,197 15 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $593 Cost: $1,804 |
$159 | 4,415 | - | 73 | - | - | $361 | - | - | - | $73 | - |
$159 4,415 kWh |
- 73 kW-months/year |
- - lb |
$361 - $ |
- - $ |
$73 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $5,600 Cost: - |
- | - | - | - | $5,600 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,600 - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.426 MODIFY WORKLOAD |
Savings: $60,000 Cost: $4,000 |
- | - | - | - | - | - | $44,000 | - | $16,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$44,000 - $ |
$16,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $77,367 Cost: $17,507 |
$5,600 | 155,547 | $5,733 | 321 | $5,600 | - | $44,361 | - | $16,000 | - | $73 | - | $5,600 155,547 kWh |
$5,733 321 kW-months/year |
$5,600 - lb |
$44,361 - $ |
$16,000 - $ |
$73 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,749 Cost: $1,150 |
$2,429 | 67,472 | $2,320 | 189 | - | - | - | - | - | - | - | - | $2,429 67,472 kWh |
$2,320 189 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |