Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2003 |
Principal Product | Corrugated Sheets |
NAICS | 322211 - Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 36 |
Plant Area (Sq.Ft.) | 107,000 |
Annual Production | 107 Thousand Feet |
Production Hrs. Annual | 6,500 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $182,446 | 2,798,121 | kWh | $0.07 |
Electricity Demand | $24,224 | 6,655 | kW-months/year | $3.64 |
Electricity Fees | $727 | - | $ | - |
Natural Gas | $110,063 | 43,660 | MMBtu | $2.52 |
TOTAL ENERGY COSTS | $549,806 | |||
RECOMMENDED SAVINGS* | $315,968 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $276,874 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,095 Cost: $5,808 |
$1,297 | 19,913 | $304 | 85 | - | - | - | - | $10 | - | $484 | - |
$1,297 19,913 kWh |
$304 85 kW-months/year |
- - MMBtu |
- - Tgal |
$10 - $ |
$484 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $950 Cost: $2,090 |
$787 | 12,103 | $80 | 22 | - | - | - | - | - | - | $83 | - |
$787 12,103 kWh |
$80 22 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$83 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $961 Cost: $1,069 |
$473 | 7,274 | $488 | 134 | - | - | - | - | - | - | - | - |
$473 7,274 kWh |
$488 134 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,526 Cost: $2,954 |
$4,102 | 63,106 | $424 | 117 | - | - | - | - | - | - | - | - |
$4,102 63,106 kWh |
$424 117 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,409 Cost: - |
$1,244 | 19,142 | $165 | 45 | - | - | - | - | - | - | - | - |
$1,244 19,142 kWh |
$165 45 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $10,710 Cost: $2,925 |
- | - | - | - | $10,710 | 3,206 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$10,710 3,206 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $392 Cost: $849 |
- | - | - | - | $392 | 159 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$392 159 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,772 Cost: $4,314 |
- | - | - | - | $1,772 | 717 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,772 717 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $5,011 Cost: $30,665 |
$4,541 | 69,862 | $470 | 129 | - | - | - | - | - | - | - | - |
$4,541 69,862 kWh |
$470 129 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,908 Cost: $44,545 |
$15,184 | 233,597 | $1,570 | 431 | - | - | - | - | $810 | - | $344 | - |
$15,184 233,597 kWh |
$1,570 431 kW-months/year |
- - MMBtu |
- - Tgal |
$810 - $ |
$344 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $8,604 Cost: $13,918 |
- | - | - | - | - | - | $8,604 | 1,200,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$8,604 1,200,000 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.451 ADD ADDITIONAL PRODUCTION SHIFT |
Savings: $261,630 Cost: $35,000 |
- | - | - | - | - | - | - | - | $261,630 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$261,630 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $315,968 Cost: $144,137 |
$27,628 | 424,997 | $3,501 | 963 | $12,874 | 4,082 | $8,604 | 1,200,000 | $262,450 | - | $911 | - | $27,628 424,997 kWh |
$3,501 963 kW-months/year |
$12,874 4,082 MMBtu |
$8,604 1,200,000 Tgal |
$262,450 - $ |
$911 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $276,874 Cost: $44,157 |
$1,717 | 26,416 | $653 | 179 | $12,874 | 4,082 | - | - | $261,630 | - | - | - | $1,717 26,416 kWh |
$653 179 kW-months/year |
$12,874 4,082 MMBtu |
- - Tgal |
$261,630 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost |