Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2004 |
Principal Product | Alluminum Ingots / Sows |
NAICS | 331314 - Secondary Smelting and Alloying of Aluminum |
SIC | 3341 - Secondary Nonferrous Metals |
Sales | $50,000,000-$100,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 187,700 |
Annual Production | 22,000 Tons |
Production Hrs. Annual | 8,064 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $222,785 | 6,999,772 | kWh | $0.03 |
Electricity Demand | $67,648 | 18,159 | kW-months/year | $3.73 |
Electricity Fees | $225,408 | - | $ | - |
Natural Gas | $1,375,837 | 310,858 | MMBtu | $4.43 |
TOTAL ENERGY COSTS | $1,891,678 | |||
RECOMMENDED SAVINGS* | $754,246 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $516,722 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2314 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT |
Savings: $158,811 Cost: - |
- | - | - | - | $158,811 | 35,849 | - | - | - | - |
- - kWh |
- - kW-months/year |
$158,811 35,849 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $212,513 Cost: $1,533 |
$(-4,949) | (-81,129) | $(-450) | (-121) | $217,912 | 49,190 | - | - | - | - |
$(-4,949) (-81,129) kWh |
$(-450) (-121) kW-months/year |
$217,912 49,190 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3412 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR |
Savings: $295,385 Cost: $90,783 |
$21,078 | 345,540 | $1,950 | 577 | $373,157 | 84,234 | - | - | $(-100,800) | - |
$21,078 345,540 kWh |
$1,950 577 kW-months/year |
$373,157 84,234 MMBtu |
- - $ |
$(-100,800) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $54,932 Cost: $8,421 |
- | - | - | - | $54,932 | 12,400 | - | - | - | - |
- - kWh |
- - kW-months/year |
$54,932 12,400 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $7,283 Cost: $1,450 |
- | - | - | - | $7,283 | 1,644 | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,283 1,644 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $24,495 Cost: $470,000 |
$21,575 | 353,753 | $2,920 | 783 | - | - | - | - | - | - |
$21,575 353,753 kWh |
$2,920 783 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $311 Cost: $282,150 |
$278 | 4,562 | $33 | 9 | - | - | - | - | - | - |
$278 4,562 kWh |
$33 9 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $516 Cost: $600,000 |
$271 | 4,441 | $22 | 6 | - | - | $81 | - | $142 | - |
$271 4,441 kWh |
$22 6 kW-months/year |
- - MMBtu |
$81 - $ |
$142 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $754,246 Cost: $1,454,337 |
$38,253 | 627,167 | $4,475 | 1,254 | $812,095 | 183,317 | $81 | - | $(-100,658) | - | $38,253 627,167 kWh |
$4,475 1,254 kW-months/year |
$812,095 183,317 MMBtu |
$81 - $ |
$(-100,658) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $516,722 Cost: $382,804 |
$21,356 | 350,102 | $1,983 | 586 | $594,183 | 134,127 | - | - | $(-100,800) | - | $21,356 350,102 kWh |
$1,983 586 kW-months/year |
$594,183 134,127 MMBtu |
- - $ |
$(-100,800) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes |