Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2005 |
Principal Product | Electroplated Steel |
NAICS | 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471 - Plating And Polishing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 24 |
Plant Area (Sq.Ft.) | 154,295 |
Annual Production | 66,000 Tons |
Production Hrs. Annual | 2,352 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $807,580 | 15,737,280 | kWh | $0.05 |
Electricity Demand | $894,216 | 93,888 | kW-months/year | $9.52 |
Electricity Fees | $(-155,282) | - | $ | - |
Natural Gas | $330,281 | 38,298 | MMBtu | $8.62 |
TOTAL ENERGY COSTS | $1,892,882 | |||
RECOMMENDED SAVINGS* | $256,546 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $224,864 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2124 INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK |
Savings: $19,946 Cost: $16,320 |
- | - | - | - | $9,345 | 1,259 | $3,123 | 1,156,783 | $7,478 | - |
- - kWh |
- - kW-months/year |
$9,345 1,259 MMBtu |
$3,123 1,156,783 Tgal |
$7,478 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $32,401 Cost: $6,800 |
- | - | - | - | $30,608 | 4,114 | - | - | $1,793 | - |
- - kWh |
- - kW-months/year |
$30,608 4,114 MMBtu |
- - Tgal |
$1,793 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $10,215 Cost: $314 |
- | - | - | - | $10,215 | 1,373 | - | - | - | - |
- - kWh |
- - kW-months/year |
$10,215 1,373 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $6,280 Cost: $46,950 |
- | - | - | - | $6,280 | 2,098 | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,280 2,098 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $8,132 Cost: $54,716 |
- | - | - | - | $8,132 | 1,093 | - | - | - | - |
- - kWh |
- - kW-months/year |
$8,132 1,093 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $513 Cost: $107 |
- | - | - | - | $513 | 69 | - | - | - | - |
- - kWh |
- - kW-months/year |
$513 69 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $4,315 Cost: - |
- | - | - | - | $4,315 | 580 | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,315 580 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $38,651 Cost: $1,902 |
- | - | - | - | $38,651 | 5,195 | - | - | - | - |
- - kWh |
- - kW-months/year |
$38,651 5,195 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $69,451 Cost: $120,000 |
- | - | $69,451 | 7,280 | - | - | - | - | - | - |
- - kWh |
$69,451 7,280 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $23,550 Cost: $2,522 |
$23,550 | 547,644 | - | - | - | - | - | - | - | - |
$23,550 547,644 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $16,926 Cost: $20,423 |
- | - | - | - | $16,926 | 2,272 | - | - | - | - |
- - kWh |
- - kW-months/year |
$16,926 2,272 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $2,545 Cost: $890 |
$2,586 | 60,290 | $(-41) | (-5) | - | - | - | - | - | - |
$2,586 60,290 kWh |
$(-41) (-5) kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $12,662 Cost: $900 |
$9,724 | 226,110 | $2,938 | 308 | - | - | - | - | - | - |
$9,724 226,110 kWh |
$2,938 308 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $10,959 Cost: $73,466 |
$5,999 | 139,459 | $4,960 | 519 | - | - | - | - | - | - |
$5,999 139,459 kWh |
$4,960 519 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $256,546 Cost: $345,310 |
$41,859 | 973,503 | $77,308 | 8,102 | $124,985 | 18,053 | $3,123 | 1,156,783 | $9,271 | - | $41,859 973,503 kWh |
$77,308 8,102 kW-months/year |
$124,985 18,053 MMBtu |
$3,123 1,156,783 Tgal |
$9,271 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $224,864 Cost: $288,072 |
$18,309 | 425,859 | $77,308 | 8,102 | $116,853 | 16,960 | $3,123 | 1,156,783 | $9,271 | - | $18,309 425,859 kWh |
$77,308 8,102 kW-months/year |
$116,853 16,960 MMBtu |
$3,123 1,156,783 Tgal |
$9,271 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption |