IAC Assessment: IC0146
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IC0146
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Illinois, Chicago
Assessment Year 2008
Principal Product Transmissions
NAICS 336390 - Other Motor Vehicle Parts Manufacturing
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $50,000,000-$100,000,000
# of Employees 186
Plant Area (Sq.Ft.) 160,000
Annual Production 21,200 Pieces
Production Hrs. Annual 2,125
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $196,637 2,713,674 kWh $0.07
Electricity Demand $46,371 8,635 kW-months/year $5.37
Electricity Fees $3,294 - $ -
Natural Gas $95,323 9,975 MMBtu $9.56
TOTAL ENERGY COSTS $353,485
RECOMMENDED SAVINGS* $87,299 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $33,123
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz) Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ $ $ MMBtu $ gal $ $ $ $
01: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$11,678
Cost:
$1,537
- - - - - - $11,678 1,222 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$11,678
1,222
MMBtu
-
-
gal
-
-
$
-
-
$
02: 2.7316 CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN Savings:
$3,159
Cost:
-
$3,159 43,878 - - - - - - - - - - - - $3,159
43,878
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
03: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$24,543
Cost:
$208,785
$2,407 33,428 $1,439 268 - - $20,697 2,165 - - - - - - $2,407
33,428
kWh
$1,439
268
kW-months/year
-
-
$
$20,697
2,165
MMBtu
-
-
gal
-
-
$
-
-
$
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,453
Cost:
-
- - - - - - $1,453 152 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,453
152
MMBtu
-
-
gal
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$815
Cost:
-
$663 9,214 $279 52 $(-127) - - - - - - - - - $663
9,214
kWh
$279
52
kW-months/year
$(-127)
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,631
Cost:
$729
$505 7,013 $215 40 - - - - - - $777 - $134 - $505
7,013
kWh
$215
40
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
$777
-
$
$134
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$548
Cost:
$211
$64 894 $5 1 - - - - - - $329 - $150 - $64
894
kWh
$5
1
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
$329
-
$
$150
-
$
08: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$541
Cost:
-
$122 1,697 $419 78 - - - - - - - - - - $122
1,697
kWh
$419
78
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
09: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,535
Cost:
$3,688
$1,105 15,350 $430 80 - - - - - - - - - - $1,105
15,350
kWh
$430
80
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$487
Cost:
$424
$138 1,920 $349 65 - - - - - - - - - - $138
1,920
kWh
$349
65
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
11: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$679
Cost:
-
$389 5,400 $290 54 - - - - - - - - - - $389
5,400
kWh
$290
54
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
12: 2.1333 CONVERT COMBUSTION EQUIPMENT TO BURN OIL Savings:
$27,915
Cost:
$32,868
$(-223) (-3,096) - - - - $23,164 2,423 $4,974 19,895 - - - - $(-223)
(-3,096)
kWh
-
-
kW-months/year
-
-
$
$23,164
2,423
MMBtu
$4,974
19,895
gal
-
-
$
-
-
$
13: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$12,315
Cost:
-
- - - - $12,315 - - - - - - - - - -
-
kWh
-
-
kW-months/year
$12,315
-
$
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$87,299
Cost:
$248,242
$8,329 115,698 $3,426 638 $12,188 - $56,992 5,962 $4,974 19,895 $1,106 - $284 - $8,329
115,698
kWh
$3,426
638
kW-months/year
$12,188
-
$
$56,992
5,962
MMBtu
$4,974
19,895
gal
$1,106
-
$
$284
-
$
TOTAL IMPLEMENTED Savings:
$33,123
Cost:
$213,837
$7,889 109,580 $3,147 586 - - $20,697 2,165 - - $1,106 - $284 - $7,889
109,580
kWh
$3,147
586
kW-months/year
-
-
$
$20,697
2,165
MMBtu
-
-
gal
$1,106
-
$
$284
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ gal $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz) Personnel Changes Primary Raw Material