Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Indiana University-Purdue University |
---|---|
Assessment Year | 2015 |
Principal Product | Plastic Bottles |
NAICS | 326160 - Plastics Bottle Manufacturing |
SIC | 3085 - Plastics Bottles |
Sales | $10,000,000-$50,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 37,314,865 Units |
Production Hrs. Annual | 5,952 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $143,291 | 2,491,200 | kWh | $0.06 |
Electricity Demand | $83,409 | 7,367 | kW-months/year | $11.32 |
Electricity Fees | $6,739 | - | $ | - |
Natural Gas | $16,716 | 1,781 | MMBtu | $9.38 |
TOTAL ENERGY COSTS | $250,861 | |||
RECOMMENDED SAVINGS* | $27,623 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,217 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,557 Cost: - |
$3,557 | 60,728 | - | - | - | - | - | - |
$3,557 60,728 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,742 Cost: $240 |
$1,742 | 29,734 | - | - | - | - | - | - |
$1,742 29,734 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $520 Cost: $144 |
$520 | 8,880 | - | - | - | - | - | - |
$520 8,880 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2313 USE BATCH FIRING WITH KILN "FURNITURE" SPECIFICALLY DESIGNED |
Savings: $4,925 Cost: $3,000 |
- | - | - | - | $4,925 | 525 | - | - |
- - kWh |
- - kW-months/year |
$4,925 525 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,961 Cost: $1,864 |
$1,398 | 23,868 | $563 | 48 | - | - | - | - |
$1,398 23,868 kWh |
$563 48 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,018 Cost: $3,232 |
$1,433 | 24,465 | $585 | 49 | - | - | - | - |
$1,433 24,465 kWh |
$585 49 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $1,865 Cost: $3,720 |
$1,865 | 31,831 | - | - | - | - | - | - |
$1,865 31,831 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $4,939 Cost: $10,200 |
- | - | - | - | - | - | $4,939 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,939 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2533 REPLACE AIR CURTAIN DOORS WITH SOLID DOORS |
Savings: $6,096 Cost: $25,603 |
- | - | - | - | $6,096 | 650 | - | - |
- - kWh |
- - kW-months/year |
$6,096 650 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $27,623 Cost: $48,003 |
$10,515 | 179,506 | $1,148 | 97 | $11,021 | 1,175 | $4,939 | - | $10,515 179,506 kWh |
$1,148 97 kW-months/year |
$11,021 1,175 MMBtu |
$4,939 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,217 Cost: $15,536 |
$8,130 | 138,795 | $1,148 | 97 | - | - | $4,939 | - | $8,130 138,795 kWh |
$1,148 97 kW-months/year |
- - MMBtu |
$4,939 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost |